What are the different NRM documents?
NRM 1: Order of cost estimating and cost planning for capital building works
NRM 2: Detailed measurement for building works
RM 3: Order of cost estimating and cost planning for building maintenance works
What is NRM?
What is CESMM?
What is the Rail Method of Measurement?
What is first principles estimating?
What is a bill of quantities?
Are you aware of the Code of Measuring Practise?
Can you give an example of some of the rules within NRM2?
For excavating and filling:
- Locate underground services
- Trial pits to locate services
- Boreholes to determine ground conditions
What’s the difference between a take off and BoQ?
How would you determine what a sufficient allowance is for an upcoming change?
Outline how you would prepare an application for payment on an NEC Option C contract
Describe how you have priced some work from first principles
When undertaking the pricing on the Fast Platform I had to calculate the square meterage of block paving
Therefore I had to break down the pricing into:
- the square meterage of paving required
- the price per square metre of materials
- the amount of paving that could be laid per hour
- the number of operatives required to required to achieve that output
- any plant or equipment required to facilitate the install