Quantification and Costing Flashcards

(7 cards)

1
Q

What are the different volumes of NRM?

A
  • NRM 1 - Order of Cost Estimating and Cost Planning for Building Works
  • NRM 2 - Detailed Measurement for Building Works
  • NRM 3 - Order of Cost Estimating and Cost Planning for Maintenance

Each volume serves a specific purpose in cost estimation and measurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the structure of NRM 1?

A
  • Introduction
  • Measurement rules for cost estimating
  • Measurement rules for cost planning
  • Tables showing rules for elemental measuring
  • Appendix

This structure provides a comprehensive guide for cost estimating and planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the structure of NRM 2?

A
  • Introduction
  • Detailed measurement of building works
  • Rules of measurement for building works
  • Appendices

The structure is designed to facilitate detailed measurement practices.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you ensure the quantities you take are accurate?

A
  • Ask the architect/engineer to scale drawings
  • Use NRM as rules on how to accurately measure
  • Measure GIFA and request the architect to confirm accuracy
  • Follow key to ensure correct items are measured
  • Undertake CostX training for software accuracy
  • Spot check against items like door widths
  • Have quantities peer reviewed by a colleague

These steps help maintain accuracy in measurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is it important to use industry standard templates and rules of measurement?

A
  • To provide accuracy and consistency
  • To ensure all parties price on the same basis
  • Contractors may not price bespoke templates
  • Disputes may require independent advice from RICS

RICS guidance emphasizes the use of industry standard templates like NRM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a vesting certificate and what other things do you need in place for valuing materials off site?

A
  • Vesting certificate: evidence that the ownership of materials will transfer from one party to another on payment
  • Off site material bond
  • Evidence that materials are present and labeled correctly
  • Insurances in place

Ensure no retention of title clause is in place in the vesting certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How are prelims split and can you give examples?

A
  • Time related
  • Fixed

Examples: Time related - cranes/hiring of plant; Fixed - cost of PPE, purchase of hoarding or welfare unit.