ABN-121 Solid Plant Malfunction:
Section 2.0: Increasing RCS Pressure
If RHR suction relief valve lifts prior to PORVs, then what might happen?
Relief valves might not re-seat.
ABN-121 Solid Plant Malfunction
→What action is taken if an RHR pump tripped?
→go to ABN-104 RHR System Malfunction
ABN-121 Solid Plant Malfunction
Section 2.0: Increasing RCS Pressure
What is the Continuous Action Step in Section 2.0?
Action / Expected Response:
Verify RCS pressure is < LTOP and RCP > 200 psid for seals
RNO:
If RCS pressure is rising:
→lower charging flow OR raise letdown flow to lower and stabilize pressure
→if LTOP actuates, ensure PORV closes when pressure is below setpoint
If RCS pressure is lowering:
→raise charging flow OR lower letdown flow to raise and stabilize pressure
→if RCP #1 seal < 200 psid, stop running RCPs
ABN-121 Solid Plant Malfunction
Section 3.0: Decreasing RCS Pressure
→What action is taken if a CCP tripped?
→What action is taken if RCS is not intact (if pressure doesn’t rise with charging flow > letdown flow)
→go to ABN-105 CVCS Malfunction
→go to ABN-108 Shutdown Loss of Coolant
ABN-121 Solid Plant Malfunction
Section 3.0: Decreasing RCS Pressure
What are steps 1 thru 4 of Section 3.0?
1) verify RCP Seal #1 > 200 psid (continuous action step)
2) verify charging flow = letdown flow
3) check RCS temp stable
RNO: control RCS temp using:
→RHR flow control valve
→CCW flow control valve
→steam dumps
→ARVs
4) verify RCS intact:
→PORVs closed
→no sump alarms
→charging and letdown matched with pressure stable
RNO:
→if RCS pressure < LTOP, ensure PORV closed or close block valve
→raise charging flow > letdown flow; if pressure doesn’t rise, match charging and letdown and go to ABN-108 for RCS leak
ABN-701 Source Range Instrument Malfunction
Section 2.0: Source Range Instrumentation Malfunction
What are steps 1 thru 4 of Section 2.0?
What is the RNO?
1) verify NO core alterations, RCS dilution, or startup in progress
2) verify at least one required SR channel operable
3) if the audible count rate was in service prior to the failure, restore by switching to the other SR channel at the audio count rate channel drawer
4) restore both required SR channels operable within 48 hours OR perform Attachment 1 within the following hour
RNO:
if less than P-6 AND less than two required SR channels operable, then suspend all core alterations and positive reactivity additions
ABN-701 Source Range Instrument Malfunction
What happens if Source Range control power fuses are removed?
What happens if Source Range instrument power fuses are removed?
Control Power Fuse Removal
→results in a Reactor Trip even with the LEVEL TRIP switch in BYPASS, unless above P-6 AND manually blocked OR unless above P-10
Instrument Power Fuse Removal
→results in a Reactor Trip unless LEVEL TRIP switch in BYPASS, OR above P-6 AND manually blocked, OR above P-10
ABN-701 Source Range Instrument Malfunction
What happens if you receive indication of a higher count rate, but you don’t know if it’s valid?
ABN-702 Intermediate Range Instrument Malfunction
What happens if Intermediate Range control power fuses are removed?
What happens if Intermediate Range instrument power fuses are removed?
Control Power Fuse Removal
→results in a Reactor Trip even with the LEVEL TRIP switch in BYPASS, unless above P-10 AND manually blocked
Instrument Power Fuse Removal
→results in a Reactor Trip unless the LEVEL TRIP switch is in BYPASS OR unless above P-10 AND manually blocked
Note:
Removing either control OR instrument power fuses could energize Source Ranges when other IR is below P-6 AND NOT blocked by P-10
ABN-702 Intermediate Range Instrument Malfunction
What could potentially happen if a reactor shutdown is performed with an IR channel failed high?
An automatic reactor trip will occur if power is lowered below P-10, unless the failed channel’s LEVEL TRIP switch is first placed in BYPASS.
ABN-702 Intermediate Range Instrument Malfunction
ABN-908 Fuel Handling Accident
What initiates the Containment Ventilation Isolation?
High containment particulate or gas activity will initiate CVI.
Operator verifies / ensures CVI once initiated.
ABN-908 Fuel Handling Accident
What is meant by putting the fuel in a safe condition / secured position?
All fuel assemblies are stored in the:
→core
→SFP
→upender (in horizontal position)
Transfer car is in the Fuel Building, AND
Fuel Transfer Tube gate valve is closed.
ABN-901 Fire Protection System Alarms or Malfunctions
What initiates the halon release sequence?
Two fire detectors in the CSR go into alarm.
ABN-901 Fire Protection System Alarms or Malfunctions
Systems Review Question:
When do the fire protection pumps automatically start?
→Jockey Pump - always on
→Electric Fire Pump X-04 - 142 psig with a 3 second time delay
→Diesel Fire Pump X-05 - 140 psig with a 10 second time delay, or on loss of control power
→Diesel Fire Pump X-06 - 140 psig with a 20 second time delay, or on loss of control power
Note: The Jockey Pump is designed to cycle on and off between 146 psig and 155 psig, but we don’t operate it that way.