Session 11.3: Subdivision Development - PD 957 & BP 220 Flashcards

(70 cards)

1
Q

What is the primary purpose of Presidential Decree 957?

A

To protect buyers of condominium and subdivision projects against misrepresentations and fraudulent activities by developers, sellers, and operators.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Presidential Decree 957, also known as the “Subdivision and Condominium Buyer’s Protective Decree”, covers which two categories of residential projects?

A

Medium Cost and Open Market residential projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

According to PD 957 site criteria, subdivision projects must avoid critical areas such as those subject to flooding, landslides, and _____.

A

unstable soil

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Under PD 957, what is the required minimum easement from the banks of rivers and streams in urban areas?

A

3 metres

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the required minimum easement from the banks of rivers and streams in agricultural areas under The Water Code?

A

20 metres.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

For a 69 KV transmission line, what is the minimum easement required by the National Power Corporation (NPC)?

A

15 metres.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

According to PHIVOLCS Resolution No. 515, development should not be located within what distance from a fault line?

A

5 metres.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In a subdivision of one hectare or more, what is the maximum percentage of the gross area that can be designated as saleable?

A

70%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In a subdivision of one hectare or more, what is the minimum percentage of the gross area that must be non-saleable?

A

30%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the minimum percentage of a subdivision’s gross area that must be allocated for parks and playgrounds when there are 20 lots per hectare?

A

3.5%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the maximum percentage of a subdivision’s gross area that must be allocated for parks and playgrounds when there are 65 lots per hectare?

A

9%.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A multi-purpose community centre is required for subdivision projects that are 1 hectare or larger or have at least how many lots/dwellings?

A

100 lots/dwellings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

An elementary school is required in a subdivision project with at least how many lots or dwellings?

A

1,500 lots/dwellings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Under PD 957, a major road used as a main access road cannot be less than how many metres wide?

A

10 metres.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A _____ is a 2-metre wide walkway used to break a block and serve pedestrians and for emergency purposes.

A

alley

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the maximum length of a block in a subdivision, after which an alley must be provided at mid-length if exceeded?

A

Blocks exceeding 250 metres must have an alley; the absolute maximum length is 400 metres.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the minimum thickness for concrete road pavement in a subdivision under PD 957?

A

150 millimetres.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the minimum compressive strength for concrete sidewalk pavement under PD 957?

A

17.2 Mega Pascal (MPa).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The crown of subdivision roads must have a slope of not less than _____ to ensure proper drainage.

A

1.5 percent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

For open market housing under PD 957, what is the minimum floor area for a dwelling?

A

42 square metres.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

For medium cost housing under PD 957, what is the minimum floor area for a dwelling?

A

30 square metres.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the Average Daily Demand (ADD) for water supply in open market and medium cost housing projects per PD 957?

A

150 litres per capita per day (LCPD).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

In a subdivision’s water system, the water tank capacity must be 20% of the Average Daily Demand plus a _____.

A

fire reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Under PD 957, street lighting must be provided per pole if the distance is 50 metres, and on every other pole if the distance is _____.

A

less than 50 metres

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is the minimum diameter for drainage pipes in a subdivision project according to PD 957?
30 centimetres.
26
In condominium development under PD 957, no development is allowed within the 5-metre mandatory easement on both sides of the _____.
Marikina Valley Fault Trace
27
For condominiums, when is a park and playground required?
When the project has a gross saleable area of 1,000 sq. metres or has ten or more condominium units.
28
What is the minimum width of a path walk for pedestrian circulation in a condominium project?
1.2 metres.
29
Under PD 957, what is the minimum area for a room intended for human habitation in a condominium?
6 square metres.
30
What is the minimum floor area for a single occupancy condominium unit?
18 square metres.
31
A 12-square-metre net floor area for a condominium unit may be allowed if it is intended for students or employees and located within a _____.
highly urbanized area
32
The minimum floor area for a family dwelling condominium unit is _____ for open market and 22 sq. metres for medium cost.
36 square metres
33
What is the parking slot requirement for condominium units with a floor area between 18 sq. m. and 22 sq. m.?
One slot for every 8 units.
34
Off-site parking for a residential condominium must be located _____ metres away or less from the project.
100
35
Off-site parking for a commercial condominium project must not be located more than _____ metres from the project.
200
36
What is the minimum road right-of-way for a condominium project, and how is it allocated?
8 metres total: 6 metres for the carriageway and 2 metres for the sidewalk/planting strip.
37
An approved preliminary subdivision development plan is valid for what period?
180 days from the date of approval.
38
A subdivision or condominium development permit is valid for a period of _____ years from issuance if no physical development is introduced.
3
39
What is a key additional requirement for the registration of a condominium project, involving the Master Deeds?
The Master Deeds must have a Declaration of Registration and Declaration of Restrictions annotated on the property title.
40
A developer cannot sell any subdivision lot or condominium unit without a _____ issued by the Board (HLURB/DHSUD).
License to Sell
41
For a subdivision project to be issued a license to sell, what is the minimum level of development required?
Land clearing and grubbing, road tracing, and an entrance gate if included in the brochure.
42
For a condominium project, what minimum development level is required before a license to sell can be issued?
Excavation as per the approved plan or excavation permit.
43
A notice of application for a license to sell must be published in two newspapers of general circulation once a week for _____ consecutive weeks.
two
44
A surety bond used as a performance bond must be callable upon demand and amount to _____ of the development cost of the unfinished portion of the plan.
20%
45
If a real estate mortgage is used as a performance bond, its value must be at least _____ of the total development cost.
20%
46
Elevators must be provided for condominium projects that are how many storeys or higher?
Five storeys and above.
47
The Certificate of Registration for a real estate broker or salesman expires on what date each year?
The first day of December.
48
Term: Single Attached
A dwelling unit with one side attached to a firewall.
49
Term: Rowhouse
A dwelling containing three or more living units abutting each other at the sides and separated by firewalls.
50
Term: Through Lot
A lot bounded on two opposite sides by roads.
51
A developer must complete a project within _____ year(s) from the issuance of the license to sell, unless an extension is granted by the Board.
one
52
A buyer may desist from further payment if a developer fails to develop a project, and can be reimbursed the total amount paid plus interest at the _____.
legal rate
53
What does Batas Pambansa Blg. 220 (BP 220) govern?
The standards and technical requirements for economic and socialized housing projects.
54
BP 220 defines socialized housing as units affordable to those whose gross family income is within _____ percent of the level determined by NEDA.
thirty (30%)
55
Term: Shell House (under BP 220)
A habitable unit with exterior walls, openings for doors/windows, plumbing fixtures, electrical wiring, and a floor.
56
Term: Complete House (under BP 220)
A shell house with all windows, doors, and partition walls for separating functional areas.
57
Under BP 220, what is the maximum length of a pathwalk or footpath?
50 metres.
58
Under BP 220, what is the minimum ceiling height for habitable rooms, measured from the finished floor to the ceiling line?
2.00 metres.
59
A mezzanine floor must have a clear ceiling height of not less than _____ metres above and below it.
1.80
60
What is the minimum clear width for a main door in an economic or socialized housing unit?
0.80 metres.
61
What is the minimum clear width for a bathroom door in an economic or socialized housing unit?
0.60 metres.
62
In socialized housing, rooms for habitable use must have window openings of at least _____ of the floor area.
10%
63
What is the minimum width for stairs under BP 220 standards?
0.60 metres.
64
The maximum riser height for stairs in socialized housing is _____ metres, and the minimum tread depth is 0.20 metres.
0.25
65
Under BP 220, what is the maximum vertical distance allowed between stair landings?
3.60 metres.
66
Who must the owner or developer donate the completed roads and open spaces of a subdivision project to?
The local government of the area.
67
Parks and playgrounds may be donated to the duly accredited Homeowners Association with the consent of the _____.
city or municipality concerned
68
What is the main mandate of Presidential Decree No. 1216, which amends PD 957?
It requires that at least 30% of the total area of residential subdivisions (one hectare or more) be reserved as open spaces.
69
Under PD 1216, areas reserved for parks, playgrounds, and recreational use are considered _____ public lands and are non-buildable.
non-alienable
70
Is it mandatory for local governments to accept the donation of completed roads, alleys, sidewalks, and playgrounds from a developer?
Yes, it is mandatory.