LCO 3.4.7 “PCS Loops - Mode 5, Loops Filled” requirement
1 SDC train shall be operable and in operation with >= 2810 gpm flow through the reactor core and either 1 additional SDC train shall be operable, or the secondary side water level of each S/G shall be >= -84%
LCO 3.4.7 “PCS Loops - Mode 5, Loops Filled” applicability
Mode 5 with PCS loops filled
LCO 3.4.7 “PCS Loops - Mode 5, Loops Filled” required action if 1 SDC train inoperable and any S/G with secondary side water level not within limit
IMMEDIATELY initiate action to restore a second SDC train to operable or initiate action to restore S/G secondary side water levels to within limits
LCO 3.4.7 “PCS Loops - Mode 5, Loops Filled” required action if 2 SDC trains inoperable or SDC flow through the core not within limits
IMMEDIATELY suspend all operations involving reduction in PCS boron concentration, and initiate action to restore 1 SDC train to operable and in operation with >= 2810 gpm flow through the reactor core
LCO 3.4.8 “PCS Loops - Mode 5, Loops Not Filled” requirement
2 SDC trains shall be operable and either 1 SDC train in operation with >= 2810 gpm flow through the reactor core, or 1 SDC train in operation with >= 650 gpm flow through the reactor core with 2 of the 3 charging pumps incapable of reducing the boron concentration in the PCS below the minimum value necessary to maintain the required shutdown margin
LCO 3.4.8 “PCS Loops - Mode 5, Loops Not Filled” applicability
Mode 5 with PCS loops not filled
LCO 3.4.8 “PCS Loops - Mode 5, Loops Not Filled” required action if 1 SDC train inoperable
IMMEDIATELY initiate action to restore SDC train to operable
LCO 3.4.8 “PCS Loops - Mode 5, Loops Not Filled” required action if 2 SDC trains inoperable, or SDC flow through the core not within limits
IMMEDIATELY suspend all operations involving reduction of PCS boron concentration, and initiate action to restore 1 SDC train to operable status and in operation with SDC flow through the reactor core within limit
LCO 3.9.4 “Shutdown Cooling (SDC) and Coolant Circulation - High Water Level” requirement
1 SDC train shall be operable and in operation
LCO 3.9.4 “Shutdown Cooling (SDC) and Coolant Circulation - High Water Level” applicability
Mode 6 with the refueling cavity water level >= 647 ft elevation
LCO 3.9.4 “Shutdown Cooling (SDC) and Coolant Circulation - High Water Level” required action if 1 required SDC train inoperable or not in operation
IMMEDIATELY initiate action to restore SDC train to operable status and in operation, and suspend operations involving a reduction in PCS boron concentration, and suspend loading irradiated fuel assemblies in the core
LCO 3.9.5 “Shutdown Cooling (SDC) and Coolant Circulation - Low Water Level” requirement
2 SDC trains shall be operable, and 1 SDC train shall be in operation
LCO 3.9.5 “Shutdown Cooling (SDC) and Coolant Circulation - Low Water Level” applicability
Mode 6 with the refueling cavity water level < 647 ft elevation
LCO 3.9.5 “Shutdown Cooling (SDC) and Coolant Circulation - Low Water Level” required action if 1 SDC train inoperable
IMMEDIATELY initiate action to restore SDC train to operable, or initiate action to establish the refueling cavity water level >= 647 ft elevation
LCO 3.9.5 “Shutdown Cooling (SDC) and Coolant Circulation - Low Water Level” required action if no SDC train operable or in operation
IMMEDIATELY suspend operations involving a reduction in PCS boron concentration, and initiate action to restore 1 SDC train to operable and in operation, and initiate action to close all containment penetrations providing direct access from containment atmosphere to outside atmosphere
What is the purpose/function of the SDC system?
- Cools PCS from 300 F to refueling temperature, 130 F, with a CCW temperature of 90 F
What is the SDC operational design pressure and temperature?
270 psia, 300 F
How are SDC from PCS MOVs, MO-3015 and MO-3016 operated?
What is the interlock associated with opening SDC from PCS MOVs, MO-3015 and MO-3016?
PCS < 275 psia (admin limit of 265 psia) to protect SDC piping from overpressure
What are the power supplies for the SDC from PCS MOVs, MO-3015 and MO-3016?
MO-3015 - MCC-1
MO-3016 - MCC-2
What is the normal position of the SDC from PCS MOVs, MO-3015 and MO-3016 while at power?
Closed with the breaker open
What is the purpose/function of RV-0401, SDC from PCS Relief Valve?
What is the purpose/function of RV-3164, SDC Suction Relief Valve?
- Relieves to the Quench Tank at 300 psig
What is a precaution if the PCS is pressurized, and MO-3015/3016 are open?
At least one of MO-3015 or 3016 have to have power in order to isolate RV-3164 to prevent an unisolable PCS leak.