STUDY TEST #1 Flashcards

(76 cards)

1
Q

Bidding documents are considered legal documents.

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Codes governing commercial construction and residential construction are different

A

(A) True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The A/E usually hires a construction manager

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The owner, contractor, and A/E are parties to the construction agreements

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

There are no differences between the AIA and EJCDC general conditions

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The drawings take precedence over the specifications

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The role of a subcontractor is the same as a material supplier

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The supplementary conditions should be coordinated with the owner/contractor agreement

A

(A) True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Preliminary Project Descriptions are legal and binding construction documents

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The contractor and the A/E review submittals for the same reasons and from the same point of view

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Division 01 sections expand and cross reference the conditions of the contract in all cases

A

(A) True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Repetition of information on both drawings and specifications is a good way to emphasize its importance

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Performance bonds as part of construction submittals are part of the procurement requirements

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The invitation to bid is designed to attract qualified bidders

A

(A) True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The volume containing the specifications, conditions of the contract, information to bidders, instructions to bidders, and the bid form is called:

A

(C) Project manual.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The documents developed to attract and assist qualified bidders in properly submitting bids are call contract documents

A

(B) False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The Agreement:

A

(B) Is the one instrument of the contract documents that binds the signing parties to the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

An alternate:

A

(C) Should be described in Division 01 and specified in the appropriate specification sections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Contract Documents consist of:

A

(A) Agreement between owner and contractor, conditions of the contract, drawings, and specifications, addenda and modifications, other documents listed in the agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Contract documents include:

A

(C) Both written and graphic portions of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Addenda are used to:

A

(A) Modify the procurement documents before award of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The agreement is part of the:

A

(D) Contract forms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Division 01 should be used to:

A

(C) Provide a logical arrangement for specifying administrative, procedural, and temporary facilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Division 01 sections relate to:

A

(B) Bidding requirements, the agreement, general and supplementary conditions, the specifications, and the drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Division 01 sections should coordinate with bidding requirements, the agreement, general and supplementary conditions, specifications, and drawings.
(A) True
26
Administrative and procedural requirements and temporary facilities are specified in:
(C) Division 01.
27
Division 01 administrative, procedural matters, and temporary facilities are cost items, the same as products and work in the technical specifications.
(A) True
28
All of the following are true about the use of standardized general conditions, such as the AIA A201 and EJCDC C-700, except:
(B) Having been reviewed initially by legal counsel, an attorney need not be consulted for the project.
29
If a contractor recognizes or has knowledge of errors, inconsistencies, or omissions in the contract documents, the contractor is responsible for reporting those errors, omissions, or inconsistencies to the A/E and may be held liable if he does not.
(A) True
30
Shop drawings, product data, and samples are considered part of the contract documents and are legal documents.
(B) False
31
Which of the following is not normally found in an agreement:
(D) Submittal requirements.
32
Procurement Documents include:
(A) Procurement requirements, which include solicitation, instructions for procurement, available information, procurement forms and supplements.
33
What is the relationship between the owner, A/E, and contractor in a design-bid-build project?
(A) The owner has a legal agreement with the A/E for design services.
34
Summarize the difference between design-build and construction management:
(A) Design-Build: The owner develops a program and the owner has one contract with a single entity to design and construct the project.
35
Construction by separate contractors provides:
(D) All of the above.
36
The Contractor shall maintain record documents at the site for the Owner
(A) True
37
Tests required by laws and regulations shall be arranged and paid by the:
(B) Contractor.
38
The Contractor is required to have a program to protect:
(D) All of the above.
39
The Contractor's duties with regard to job safety includes designating a responsible individual whose duties at the site include accident prevention.
(A) True
40
The A/E will:
(A) Endeavor to guard the Owner against defects and deficiencies in the Work.
41
The Contractor shall not be required to contract with any one to whom he has made reasonable objection.
(A) True
42
The Contractor shall not contract with nor be required to contract with Subcontractor against whom reasonable objection has been made by:
(D) All of the above.
43
The A/E’s approval of Shop Drawings is:
(A) For conformance with the information given and design concept.
44
In the event the A/E fails to approve a Shop Drawing covering a major portion of the Work in sufficient time, the Contractor shall:
(C) Write the A/E requesting promptness in reviewing Shop Drawings.
45
The method for computing credits for change orders should be described in:
(C) The general and supplementary conditions.
46
The owner must sign:
(B) Change orders.
47
If the owner accepts defective work, a change order may be issued to reflect an appropriate adjustment in the contract sum.
(A) True
48
Claims alleging an error or omission by the A/E should initially be referred for action to the:
(C) A/E
49
The owner may order additions or deletion in the work without invalidating the contract.
(A) True
50
The contractor is not obligated to execute a change in the work authorized by the owner until an agreement on an adjustment of the contract sum has been reached.
(B) False
51
Under SectionFormat, the Parts are entitled:
(C) General, Products, Execution.
52
Under SectionFormat, schedules such as painting or hardware belong in:
(C) Part 3.
53
In specification writing, the indicative mood causes unnecessary wordiness and monotony.
(A) True
54
Applications of MasterFormat include:
(C) Project manuals, relating drawing notations to specifications, and cost classification.
55
The A/E observes construction:
(B) To guard the owner against defects and deficiencies.
56
The contractor is not required to:
(C) Pay assessments determined by authorities having jurisdiction.
57
Which method of specifying should be used to specify the end results to be achieved rather than the means for achieving the desired results?
(B) Performance.
58
Which of the following are best designated on the drawings (Choose all that apply):
(B) Location. (D) Dimension and size. (E) Shape and form.
59
Which of the following are best designated on the specifications (Choose all that apply):
(A) Specific requirements. (C) Quality of materials.
60
Quality control activities occur before or while accomplishing the work or service.
(B) False
61
Quality assurance activities occur before or while accomplishing the work or service.
(A) True
62
Marked up or corrected contract drawings that indicate changes incorporated into the work during construction are called:
(B) Record drawings.
63
A particular material may be indicated several times on the drawings but is specified in how many locations:
(A) One.
64
To avoid confusion, who should take responsibility for enforcing consistent terminology:
(B) Specifier.
65
Resource drawings serve what purpose:
(B) Show construction related to the work, but which is not indicated in the contract.
66
An Allowance is a set amount included in the base bid.
(A) True
67
Unit Price: Amount determined by number of units at the agreed upon unit cost.
(A) True
68
Alternate: A defined portion of the work that is priced separately, which the contractor may choose to add to the project.
(B) False
69
Section drawings are cut vertically through and perpendicular to project materials to:
(B) Show detailed arrangement.
70
Defective tile work has appeared on a bonded job before final payment. If the contractor, after having been properly notified in writing by the owner, fails to begin correcting the defective work within the time specified in the general conditions, the owner may:
(B) Correct deficiencies and issue an appropriate change order reflecting deduction for the cost of correcting the deficiencies, including compensation for the A/E's additional services and expenses from payments then or thereafter due the contractor.
71
The contractor shall promptly correct defective work rejected by the A/E:
(A) If observed before substantial completion. (B) If observed after substantial completion. (C) All of the above.
72
Substitution procedures:
(B) Are specified in Division 01.
73
Substitutions may do all of the following except:
(A) Limit competition.
74
If the contractor installs an item of work in accordance with the contract documents, knowing it is in violation of the governing building codes without first informing the A/E, he is responsible for the cost of the replacement.
(A) True
75
The warranty period begins:
(B) On the date of substantial completion.
76
The contractor, during foundation excavations, uncovers a large telephone trunk line. The line is not located on the construction documents. The contractor should:
(C) Notify the owner and continue with excavation in areas unaffected by the trunk line.