What is a form of tender?
What information is typically included in the form of tender?
When seeking tenders for construction work, in addition to the actual price for the work, what additional information might be requested?
Qualitative submission including:
- Demonstration of previous experience.
- Proposed team and hierarchy.
- Proposed methodology.
- References.
- Programme.
- H&S information.
- VE proposals.
Once tenders have been submitted, what should be examined for compliance with the ITT?
What happens if a tender is submitted late?
Public sector: tender should NOT be accepted.
Private sector: at the discretion of the employer. Advise that the safest option is not to consider as risk of collusion, bid-rigging.
Would you open a late tender submission for a school project?
What is the danger of accepting a very low tender submission?
How do you deal with qualifications within the tender submission?
How would you deal with errors identified in the tender submissions?
Alternative 1: Confirm or withdraw
Alternative 2: Confirm or amend
What would you do if you considered a contractor submitting the lowest tender to be in financial difficulty?
On what grounds would you advise the client to retender?
How would you deal with a front-loaded tender?
How could you reduce the risk of contractors pulling out during the tender process?
What is a contract sum analysis under design & build procurement?
What information is typically included in a tender analysis report?
If the tender was received on time, but the works were delayed and did not commence until a few months later, what would you need to check?
If the contractor (in their tender return) put a cost against an item and marked it as provisional, what would you do?
If you think the delivery programme is tight, how can you give comfort to the contractor regarding liquidated damages (to avoid them excessively pricing in their tender sum)?
If you think the delivery programme is tight, how can you give comfort to the contractor regarding liquidated damages (to avoid them excessively pricing in their tender sum)?
What is the purpose of a pre-tender estimate?
What happens if the tender prices are higher than the pre-tender estimate?