Planning answers? (6)
Key Planning Documents (3)
What does a scope statement include? (4)
Define statement of work
A narrative description of all work to be done
Define work breakdown structure (wbs)
A deliverable oriented hierarchical decomposition of the total scope of work
Critical rule of WBS
A represents 100% of the project scope. Work not in the WBS is out of scope
Components of a WBS (3)
Level one: the project
Level two: major deliverables broken down into smaller components
Level three: work package (manageable, assignable, estimatable tasks)
Purpose/importance of a WBS (4)
Techniques to build a WBS (4)
Responsibility assignment matrix: RACI Codes
R-esponsible (does the work)
A-ccountable (has final authority)
C-onsulted (two way communication)
I-nformed (one way communication)
Define communication plan
Specifies who needs what information, when, in what format and by whom
Define activity
A component of work with a duration
Define predecessor
An activity that must be fully or partially completed before another can start
Define successor
An activity that comes after
Define network diagram
A visual flowchart of activities and their dependencies like a map
Define critical path
The longest sequence of dependent activities in the project. A determines the shortest possible project duration. No float or slack on the critical path
Define float or slack
The amount of time an activity can be delayed without delaying the project finished date
Define early start or early finish
The earliest an activity can start or finish
Define late start or late finish
The latest unactivity can start or finish without delaying the project
What are the two main diagramming method
Steps in the scheduling process (5)
Advantages of a gantt chart