When is TRM 3.1.2.1 Charging Pumps / Flow Paths - Shutdown Applicable?

MODE 4
MODE 5 w/ Loops filled

What are your ≤ 1 hr action(s) if no boron injection flowpaths are available, or all CCPs inoperable, or all emergency power sources are inoperable while in MODE 4 or MODE 5 w/ loops filled?

Suspend all Positive Reactivity Additions that could result in a loss of SDM or boron concentration [Immediately]

What are the boron injection flowpaths required in MODE 4 or MODE 5 with RCS loops filled?
Method 2:
RWST
CCP

When is TRM 3.1.2.2 Charging Pumps / Flow Paths - Operating Applicable?
MODES 1-3
What borated sources of water must be available in MODE 5-6?
BAT:
≥ 3200 gal
≥ 7000 ppm Boron
≥ 65 ˚F
RWST:
MODE 5: 122,000 gal
MODE 6: 33,000 gal
2800 ppm - 3000 ppm Boron
Need one of the above.

What are your ≤ 1 hr action(s) if no borated water sources are FUNCTIONAL in MODES 5-6?

AND

What borated sources of water must be available in MODE 1-4?
BAT:
≥ 27,000 gal
≥ 7000 ppm Boron
≥ 65 ˚F
RWST:
≥ 458,000 gal
2800 ppm - 3000 ppm

What are your ≤ 1 hr action(s) if the Boric acid storage system is lost in MODES 1-4 and is being used as one of the boric acid sources?


When is TRM 3.1.2.7 Boron Injection System - Shutdown Applicable?

MODE 5 w/ RCS loops not filled
MODE 6

What are your ≤ 1 hr action(s) if you have no CCP or LHSI pumps capable of taking suction on the RWST or BAT during MODE 5 w/ RCS loops not filled or MODE 6?

AND

What are your ≤ 1 hr action(s) if DRPI indication is lost in MODES 3-5 with the Rx Trip breakers shut and Rod control capable of withdrawing rods?


What are your ≤ 1 hr action(s) if all PZR safety valves are nonfunctional in MODES 4-5?

AND

What is the PZR HUR, CDR, and Aux Spray ∆T Limits?
HUR: 100 ˚F/hr
CDR: 200 ˚F/hr
Aux Spray ∆T: 621 ˚F

What are your ≤ 1 hr action(s) if you violate the PZR HUR, CDR, or PZR spray max ∆T?

AND
OR
AND

When is TRM 3.4.11 Rx Vessel Head Vents Applicable?

MODES 1-4

What are the ≤ 1 hr action(s) if ≥ 1 Rx head vent valves are nonfunctional in MODES 1-4?

Note:
Continued S/U / Power operation may continue if valves in vent path are closed with power removed.

When is TRM 3.6.2.1 Containment Spray System Applicable?

MODES 1-4

When is TRM 3.6.4.1 Hydrogen Analyzers Applicable?

MODES 1-2

Only action is if ≥ 1 Hydrogen Analyzers nonfunctional, get it back as soon as practical.