What is a fixed position layout? What products is it used to make?
the product does not move throughout production, the resources and manpower do.
eg. ships, buildings and trains
What is process layout? what are some examples?
machines are grouped into departments or stations according to the operations that they perform.
eg. pressing department, lathes department
What is product layout? what are some examples?
machines are grouped according to the product manufacturing sequence.
called manufacturing lines
ex. used for high volume component parts
What are cellular layouts? what are some examples?
What are the advantages of cellular layouts?
What is a task?
a set of necessary steps that the work gets decomposed into
-is considered the smallest assignable unit to a cell
What is a workstation?
the logical organization of specific manufacturing or assembly equipment to perform tasks
-the number should be as small as possible
What are some disadvantages of cellular designs?
- more works needed for movement of materials
What is takt-time? what is the calculation for takt time?
is the time between starting to work on one unit and starting the next.
What is cycle time? How is it calculated?
is the normal time to complete an operation on a product in each workstation
Calculation:
sum of the task times that a product requires at each station
Preferably, should cycle time be more the takt-time? why?
Cycle time should be less then or equal to takt time. Because if it is not, orders will get behind and you will have late orders, unhappy customers and more expediting of products.
What is idle time? how is it calculated?
Paid time during which an employee, or machine is not doing anything productive.
What is a precedence diagram?
It is a diagram that shows the order of the parts being manufactured
What is group technology?
is a tool used in engineering and production departments to identify similar products.
What is a time study?
the methods used to determine the standard time for an operation
- the time qualified worker needs to carry out a specific task , working in a normal rhythm during a work day
What is leveling production?
it is a prerequisite required for a cellular layout transformation
-corresponds to the production and scheduling strategy
What are advantages to multifunctional workers?
What are the prerequisites for cell disigning?
What is the main goal of line-balancing?
What are the steps in line balancing?
When is a task eligible to be assigned?
it it has not yet been assigned and all that precede it have been
What are the heuristics?
-total number of following tasks- choose the task with the largest total number of following tasks
if more then two pick the one with the longest time
-individual durations -which has the longest time
if two pick the one that has the longest total number of following tasks