How were you appointed?
Through a professional services framework contract
How does a professional services framework work?
How did you establish the design requirements?
I met with the client on site to discuss the work required and then subsequently attended a meeting with the client to record the full brief in writing
Who were the stakeholders and how did you identify them?
What did you consider during your desktop study?
What did you include in your feasibility study?
At which RIBA stage would you complete a feasibility study?
Stage 1 - Preparation and Brief
What is involved at the other RIBA stages?
How did you establish the programme?
By breaking down the different tasks and trades required to complete the works and making an assessment based on past experience of projects of a similar nature
How did you put together the budget estimate?
An outline schedule of work was completed and each item was priced with a QS based on current unit rates and experience from previous projects
As you were the designer, what level of PII did you have?
I am covered by my company’s PI insurance, which meets the RICS minimum level of indemnity required based on the company’s turnover, as well as the requirements of the professional services framework I was appointed under
Tell me about the budget reallocations.
You say if you had more time you could have taken a more holistic approach. How would this have helped matters?
More time would have allowed me to sit down with the client and potentially identify the works required, the timescales involved and whether there were any other properties in their ownership that would offer a more suitable alternative before designs were developed and tenders issued
How did you appoint the M&E designers?
They were appointed directly by my company, with their services being covered in my company’s own fee and with a back-to-back agreement in place, reflecting the terms of my company’s own appointment (e.g. level of PII, payment terms, exclusions etc.)
Who took liability for the M&E designers?
My company were responsible for the delivery and content of the M&E submission
How did you ensure the M&E designers were competent?
The appointment was based on previous working relationships with the client, so they had already been vetted by my company’s supply-chain management team and fee rates had been agreed under the professional services framework
Why did you choose JCT MW?
What alternative contracts could you have used and why did you not use them?
NEC3 EC Short Contract may have also been suitable, however this form was less familiar with the client and their procurement team had already identified their desire to proceed with JCT MW based on consistency with other similar projects
How would your tender differ if you used an NEC form of contract?
The contract terminology and mechanisms would need to be identified and changed to match the provisions in the NEC form, including all preliminary information contained within the Works Information, request for an activity schedule and programme (which are integral to NEC contracts) and formation of a risk register instead of provisional sums
What procurement options did you advise on?
On this project, this was something that was decided by the client’s in-house procurement department
Considering the time constraints, would any other procurement options have been more suitable for this project?
Using a pre-approved contractor that would have been called off a framework based on the estimated project cost may have allowed more time in the design stage without going through the lengthy tender process, however the client wanted a more competitive value by opening the opportunity to local contractors
How did you decide on which contractors to tender to?
There were no contractors chosen prior to tendering, as a single-stage open tendering procedure was used
What is the difference between the different tendering procedures?
What are the advantages and disadvantages of e-tendering?
Advantages:
Disadvantages: