Where was the dry rot?
Affected the timber floor joists initially and had spread through floor boards, skirtings and the wall plaster to affect timber window lintels, all on the west elevation
What was the cause of the dry rot?
A defective downpipe on the west elevation was causing the timber joists embedded into the solid masonry wall to become damp, and the lack of ventilation within the building created the right enviornment for dry rot to spread
Other than dry rot, what other types of timber decay are you familiar with?
Wet rot and wood-boring insect infestation
What is the difference between wet and dry rot?
How can you tell the difference between wet and dry rot?
You refer to a specialist undertaking the dry rot survey initially, however ultimately you chose to undertake your own inspection to establish the current state of infestation. Does this mean you are a specialist in dry rot?
Not a specialist but competent in identifying the extent of dry rot
Would you complete a survey and remedial works specification for dry rot?
Yes, however I would seek further input from other parties if necessary (e.g. structural engineer if replacing structural timbers, or a conservation officer in historic buildings)
What remedial works would you recommend for dry rot?
Set out in BRE 299 (Dry Rot: Recognition and Control):
What made you think the extent of the rot could have worsened since the report was completed?
From previous research and BRE guidance, I learnt that dry rot can rapidly spread in the correct conditions and as the building had been left vacant and unventilated, I suspected this could be a possibility
In option 1, how would you have issued the variation for additional rot remedial works?
How would you have determined the value of the provisional sum to include for the unforeseen rot remedial works?
I would have assessed the implications this may have caused with a QS and estimated a value, however as the provisional sum would have been undefined, the risk would have lied with the client and was one of the reasons I did not advise on taking this route
If the unforeseen works would have been covered by a provisional sum, what kind of provisional sum would it have been and why?
Undefined, as the full extent of the works could not have been established
In option 1, why would the additional cost for delays post-contract be greater than those caused pre-contract?
Because pre-contract there would have been no contractor on board, whereas post-contract the contractor may have been entitled to claim loss and expense
How did you establish the new area of rot?
By revisiting the building and undertaking further investigations yourself, did your client have a problem with you disobeying his instruction to proceed with option 1?
No, they commented that they appreciated my professionalism the additional advice I had sought to give them
Why could you not have stuck to the programme and then issue a tender amendment once the revised dry rot report had been received?
I felt the dry rot report and the extent of the remedial measures was critical for the tendering contractors in order to plan their works and price accurately, and ultimately may have deterred contractors from bidding if this information was tentative
How was the client able to keep extending the end users’ current tenancy?
I believe the transparency of information within the client’s team was not sufficient and information was not updated regularly, causing my contact to think there was less flexibility in the programme than there actually was
Why did you receive the dry rot report late?
If the client had included the dry rot works in your instruction, how could this have improved matters?