What caused the drain to become defective?
This was unconfirmed as the excavations were not undertaken in the end, however I suspected it may have been a combination of extra load due to recent resurfacing of the area and roots from adjacent trees attacking the displaced joints
What tests could you have undertaken to determine whether the drain was defective?
What impact could the defective drain have had on the existing building?
Any change in ground water levels as a result of a leaking drain may have undermined the building’s foundations, however there was no evidence of movement in this case
Did you need to consider any surrounding buildings before undertaking the excavations?
Had there have been any buildings within a closer proximity, I would have considered issuing a Notice of Adjacent Excavation under the Party Wall etc Act, however there were no structures within the required distance for such provisions to apply
Would a building surveyor design drainage?
They can do, however they may seek further advice from a structural engineer or specialist drainage contractor
Do you feel you are capable of assessing and designing drainage?
As the works in this case were localised and minor in complexity, I felt competent in its design by considering the appropriate guidance
How did you design the drainage?
What type of pipe was replaced and what did you replace it with?
The existing drain was vitrified clay pipework and I proposed the replace the defective section with clay pipe to match
How would the new underground pipe have been connected to the existing pipe?
I specified the installation of adjustable couplings that contained adjustable collars at each end made from a durable rubber material that could be tightened by stainless steel ‘jubilee clips’ to connect the two sections of pipe in a line
How did you specify the new build-up of the ground from the drainage to the surface?
I looked in Approved Document H and as I was specifying rigid pipework, it had to sit on 100mm of granular material (graded 5-10mm) up to half the depth of the pipe and then selected fill (free from stones >40mm and lumps of clay >100mm) 150mm above the top of the pipe, with the rest of the excavation backfilled as normal
Does the bedding that sits around the underground drain need to be compacted?
Yes, a maximum compaction fraction of 0.3 was detailed in Approved Document H
Was the defective pipe for foul water or surface water and why would this have an impact?
It was a combined drainage system receiving both foul and surface water, which may have had an impact when specifying the size of the pipework, however this was not a factor for this minor like-for-like repair
In option 2, how would you have connected the new above ground drain to the existing SVP?
A section of the existing SVP would have been removed and replaced with a branch junction connector, providing a ‘T’ junction for the new pipework, all connected with adjustable couplings
In option 2, to enable you to install more than one toilet, why could you not have used a shallower gradient?
In option 2, what other options did you consider to allow for the installation of more than one toilet?
What did you consider in terms of maintenance of the drainage system?
What methods are available for connecting uPVC pipework?
How did you assess which drainage option was the most cost-effective?
I liaised with a QS who considered current market rates based on pricing guidance such as BCIS, as well as costs for similar work on recent projects
What were the respective costs and lifespans of the different drainage options?
How does the process of relining the drain work?
How was the CCTV survey commissioned?
They were appointed directly by my company, with their services being covered in my company’s own fee and with a back-to-back agreement in place, reflecting the terms of my company’s own appointment (e.g. level of PII, payment terms, exclusions etc.)
Who took liability for the CCTV survey?
My company were responsible for the delivery and content of their submission
You say replacing the drain would have had increased quality control due to building control involvement. Do you feel you would have not been able to provide this quality control yourself?
I would have provided quality control, however there would have been increased control due to an additional party who would have also had to provide a compliance certificate for the works
Why do you feel the client would have selected option 2 had they not have been able to extend the end-users’ current tenancy?
I believe that due to the quality concerns and risk of future problems with the lining option, the client would have preferred not to take the risk and instead compromise on the number of toilets