What is a Project Network Diagram?
A flow chart that graphically depicts the sequence, interdependencies and start and finish times of the project activities.
How does a Project Network Diagram work?
Every activity on the network diagram must be completed for the project to finish.
What are the Benefits of a Project Network Diagram?
What is the terminology used (when Constructing a Project Diagram).
What is an activity (or task)?
An element of the project that requires time – e.g., A, B, C, D, etc.
What is a Path?
A sequence of connected, dependent activities.
What is a Critical Path?
The longest path through the network that allows for the completion of all project-related activities.
What is dependency?
Dependency relates to the sequencing of project activities.
What are the different types of dependencies?
We must understand the type of dependencies required for each activity on our project.
What is a successor?
An activity that is done directly after another activity.
What are Mandatory Dependencies (Hard Logic)?
Inherent in the nature of the work itself – e.g., scrape off old paint, then apply primer, then paint the house.
What are Discretionary Dependencies (Soft Logic)?
Defined by the project team - e.g., paint room 1 first and then paint room 2.
What are External Dependencies?
Involve relationships between project and non-project activities – e.g., a shared hardware platform ordered by another department.
What is a predecessor?
An activity that is done directly before another activity.
What are the different types of dependency relationships?
What is a Finish-to-start relationship?
The subsequent activity cannot start until the preceding activity is finished.
- E.g. car manufacturing: painting can’t begin until the welding is finished.
What is a Start-to-start relationship?
The subsequent activity can start AFTER the preceding activity has started.
- E.g. trenching 1km and then laying the pipe while continuing the trenching activity for the next kilometre.
What is a Finish-to-finish relationship?
The finish of the subsequent activity depends on the finish of the preceding activity.
- E.g. testing the prototype can start while it is still developed, but has to finish after the prototype has been fully developed.
What is a Start-to-finish relationship?
The finish of the subsequent activity depends on the start of the preceding activity.
- E.g. the documentation of a system cannot finish before the testing has started.
What is the importance of Project Network Diagram?
What are the two complementary approaches (of Project Network Diagrams?)
- Backward pass → latest times
What three questions do you need to answer (for forward pass computation?)
What three things do you need to remember (for forward pass computation?)
What four questions do you need to answer (for backward pass computation?)