Reasons for Reducing Project Duration.
Options when resources are NOT constrained.
Options when resources are constrained.
Other approaches to accelerating a project.
Determining the activities to shorten.
Look for critical activities (on the critical path) that can be shortened, with smallest increase in direct cost per time.
Project Costs.
Direct Costs.
Indirect Costs
Optimal time-cost trade-off (step 1)
Prepare a network.
Optimal time-cost trade-off (step 2)
Optimal time-cost trade-off (step 3)
- Slope = (CC-NC)/(NT-CT).
Optimal time-cost trade-off (step 4)
Optimal time-cost trade-off (step 5)
Optimal time-cost trade-off (step 6)
The total crash cost/period of all selected activities should be the smallest.
What if Cost is the Issue? Then, you should..