Reasons for reducing project duration.
Monitoring and controlling projects (definition)
Comparing actual performance against plan to identify deviations.
What deviations?
Crashing (formula)
slope = crash cost - normal cost / normal time - crash time
Changes (cus..)
Due to customer requests - add new features or taking out original features.
Changes (risk..)
Due to risk event - implementation of contingency plan.
Changes (pro..)
Due to suggestions from project team members - improvement.
Time Management (sch..)
Schedule control to..
Cost Management (cost control to..)
Cost Management (cost control for..)
Baseline.
The primary reference point against which we measure changes in our project
Tracking Gantt Chart.
Used to monitor and control projects.
- Planned = 1 million. Why?
EVM (definition)
A systematic project management process used to find variances in projects based on the comparison of worked performed and work planned.
Term (ear..)
Earned Value or BCWP
- Percent of original budget earned from work completed
Term (pla..)
Planned budget or BCWS
- Cumulative time phased baseline of the value of the work scheduled
Term (act..)
Actual cost or ACWP
- Actual cost incurred from accomplishing work
Term (cos..)
Cost Variance
- Difference between EV and AC for work completed to date
CV = EV - AC or = BCWP - ACWP
Term (sch..)
Schedule Variance
- Difference between EV and and the baseline line to date
SV = EV - PV or = BCWP - BCWS
Term (bud..)
Budgeted at Completion (BAC)
- Total budgeted cost of the baseline
Term (var..)
Variance at Completion (VAC)
- Indicates actual cost at completion
VAC = BAC - EACe derived from estimators in field
VAC = BAC - EACf derived from a formula
Performance Index (CPI)
Cost Performance Index
- Measures cost efficiency of work accomplished to date
(CPI = EV/AC)
Performance Index (SPI)
Scheduling Performance Index
- Measures scheduling efficiency
(SPI = EV/PV)
Performance Index (ETC)
Estimate to Complete
= (BAC-EV)/CPI