B101
Standard form of agreement between owner and architect
Consultants relationship to B101
The consultants of the Architect shall require each such consultant to be bound to the Owner by terms of this Agreement and the Contract Documents, and to assume toward the Owner all the obligations and responsibilities which the Architect assumes toward the Owner.
What are the types of insurance that an architect may have? B101
General Liability
Automobile Liability
Worker’s Compensation
Professional Liability
Architect coordination of services. B101
The Architect shall coordinate its services with those services provided by the Owner and the Owner’s consultants. The Architect shall be entitled to rely on the accuracy and completeness of services and information
furnished by the Owner and the Owner’s consultants.
schedule for the performance of the Architect’s services B101
During Schematic Design Phase Services the architect: B101
The Schematic Design Documents shall consist of: B101
drawings and other documents, a site plan, if appropriate, and preliminary building plans sections and elevations;and may include some combination of study models, perspective sketches, or digital modeling. Preliminary selections of major building systems and construction materials shall be noted on the drawings or described in writing.
Schematic design and environmental issues B101
Design Development Documents are based on? B101
2. the Owner’s authorization of any adjustments in the Project requirements and the budget for the Cost of the Work
Design Development Documents consist of: B101
drawings and other documents
including plans, sections, elevations, typical construction details, and diagrammatic layouts of building systems to fix and describe the size and character of the Project as to architectural, structural, mechanical and electrical systems, and such other elements as may be appropriate. The Design Development Documents shall also include outline specifications that identify major materials and systems and establish in general their quality levels.
During Design Development the Architect performs what services? B101
2. Update the estimate of the Cost of the work.
Construction Documents Phase Services are based on? B101
2. the Owner’s authorization of any adjustments in the Project requirements and the budget for the Cost of the Work
The Construction Documents consist of? B101
shall consist of Drawings and Specifications setting
forth in detail the quality levels of materials and systems and other requirements for the construction of the Work.
During the development of the Construction Documents, the Architect shall assist The Owner in the development and preparation of: B101
(1) bidding and procurement information that describes the time, place and conditions of bidding,
including bidding or proposal forms;
(2) the form of agreement between the Owner and Contractor; and
(3) the Conditions of the Contract for Construction (General, Supplementary and other Conditions).
(4) The Architect shall also compile a project manual that includes the Conditions of the Contract for Construction and Specifications and may include bidding requirements and sample forms.
During CDs the architect does what in regard to estimates? B101
Updates the estimate for the cost of the work
During the Bidding or Negotiating Phase the Architect assists the owner in? B101
establishing a list of prospective contractors.
(1) obtaining either competitive bids or negotiated
proposals;
(2) confirming responsiveness of bids or proposals;
(3) determining the successful bid or proposal, if any; and,
(4) awarding and preparing contracts for construction.
Bidding Documents shall consist of? B101
bidding requirements and proposed Contract Documents
The Architect shall assist the Owner in bidding the Project by B101
.1 procuring the reproduction of Bidding Documents for distribution to prospective bidders;
.2 distributing the Bidding Documents to prospective bidders, requesting their return upon completion of the”bidding process, and maintaining a log of distribution and retrieval and of the amounts of deposits, if any, received from and returned to prospective bidders;
.3 organizing and conducting a pre-bid conference for prospective bidders; .
.4 preparing”responses to questions from prospective bidders and providing clarifications and interpretations of the Bidding Documents to all prospective bidders in the form of addenda; and
.5 organizing and conducting the opening of the bids, and subsequently documenting and distributing the
bidding results, as directed by the Owner.
Substitutions during bidding phase: B101
he Architect shall consider requests for substitutions, if the Bidding Documents permit substitutions, and shall
prepare and distribute addenda identifying approved substitutions to all prospective bidders.
Proposal Documents shall consist of: B101
proposal requirements and proposed Contract Documents
The Architect shall assist the Owner in obtaining proposals by: B101
.1 procuring the reproduction of Proposal Documents for distribution to prospective contractors, and , requesting their return upon completion of the negotiation process;
.2 organizing and participating in selection interviews with prospective contractors; and
.3 participating in negotiations with prospective contractors, and subsequently preparing a summary report of the negotiation results, as directed by the Owner.
Substitutions in regards to proposals: B101
The Architect shall consider requests for substitutions, if the Proposal Documents permit substitutions, and shall prepare and distribute addenda identifying approved substitutions to all prospective contractors.
When are proposals and proposal documents used? B101
They are part of the Bidding or Negotiating phase. The proposals are “Negotiated proposals” and the architect must provide either assistance in bidding or in Negotiating but not both.
General Construction Phase Services of the Architect B101