What is infinite loading
Scheduling that calculates the capacity needed at work centers in the time period needed without regard to the capacity available to do the work.
What is finite loading
Scheduling that loads work centers up to a predetermined amount of capacity.
What is forward scheduling?
Schedule that determines the earliest possible completion date for a job.
What is backward scheduling?
Starts with the due date for an order and works backward to determine the start date for each activity.
-Determines latest time to start without being late
- This method is useful for ensuring that deadlines are met.
What is the Theory of Constraints (TOC)?
What is an internal resource constraint?
A regular bottleneck.
a resource or piece of equipment that limits output.
Example: One slow machine on an assembly line.
It occurs when a specific resource limits the overall capacity of the system.
What is a market constraint?
The condition that results when market demand is less than production capacity.
This constraint can lead to underutilization of resources.
What is a policy constraint?
The condition that results when a specific policy dictates the rate of production.
rules, procedures, or management decisions that limit performance.
Policies can restrict flexibility and affect overall efficiency.
Advantages of Inifinite Loading ?
Gantt Chart
Load Chart
Chart that visually shows workloads relative to the capacity at a resource
Progress chart
Visually shows planned schedule compared to actual performance