In addition to the scope transfer, can you please explain what other VM/VE options were considered?
Some of the items we considered as part of the value engineering was:
Explored:
Approved:
How did your cost plan compare with the contractor’s sum?
The contractor’s sum was C.£13m, which when combined with the risk register and other project additions came to about £16.7m, so C.£300k cheaper than the budget and 50k over the revised cost plan value once the MEP elements of 5-6 were removed.
You mention there was a 3% risk allowance in your cost plan to cover for the premium of a non-competitive tender; how did you get to this conclusion?
Benchmarking.
Within the London team, there have numerous examples of fitout projects that have started as negotiated tenders but were non-viable, and then when re tendered they have shown a trend of between 2%-5% construction costs savings.
What other risk allowances did you include in your cost plan?
There was a fully costed risk register. The big ticket items were the employer change allowance, a general inflation allowance and supply chain default.
What contract mechanism did you advise the client to engage the contractor and their supply chain earlier?
We used a PCSA to engage with the contractor in order to gain insight on stage 3 design, costs, buildability etc.
The reason we used a PCSA even though we were direct awarding was because the university still needed a mechanism for aborting the project if the cost exceeded their budget.
How did you advise your client on procurement? What other procurement options did you consider?
I advised the client about the inflexibility of direct awarding but the decision had been made at an earlier stage. As part of my advice relating to the key issue I offered to the client, we explored other competitive methods but it prolonged the programme and affected the occupation date.
Why was NEC Option A selected over JCT D&B?
You talk about proactive cost management, what do you mean by this?
Proactive cost management involves anticipating, planning, and controlling costs throughout a project’s life cycle to ensure financial efficiency and prevent cost overruns.
How did you report value for money when directly appointing a main contractor?
On Brent Cross the main two ways I reported value for money was through comparing contractor costs to rates from benchmark schemes in London, as well as to the rates used on the sister scheme in Sheffield once location and inflation had been accounted for.
What was the justification for choosing Option A over Option B or C?
The project was simple, with a well defined scope and a low risk profile, so it was more suited to an Option A or Option B than a C.
Option A was chosen as it has the simplest payment process, providing greater cost certainty and less risk than Option B as it is not re measurable, the contractor is at risk for incorrectly measuring the quantities.
What is the purpose of the alliance contract between SHU and BAM?
The NEC4 Alliance Contract is designed to foster close collaboration among all parties involved in a construction project.
It introduces shared goals, integrates teams, encourages long term relationships, promotes more efficient risk management, promotes transparency as all parties sign up to a single set of terms.
It is usually employed on large projects with multiple stakeholders and parties, such as by Highways England for the conversion of hard shoulders into smart motorways.
Why did you recommend a design and build contract over a traditional one?
I would use a D&B contract where the client wished for the contractor to be responsible for the design. Usually this is because the client will benefit from the contractor’s knowledge and can increase the buildability of the design, whilst also transferring the design risk on to the contractor.
You mentioned the splitting the MEP installation between the floors in order to reduce costs, can you explain some of the issues this may cause?
You said that you maintained continuous communication with both the contractor and the client team, what form did this take?
I maintained continuous communication through various forms.
Re-occurring teams meetings, progress, risk, etc.
Regular calls and emails.
Site visits.
What was your total construction cost?
What was your total contingency?
What was value of partitions?
£13m Construction Cost
£390k (3%) non-competitive pricing risk
£1.235m risk contingency remaining
£2m professional fees
£350k SHU Estates resource
Biggest package in construction was partitions and ceilings at £4m, circa 30% of cost.
What was the project duration? What was the start date? What was the longest activity on the programme?
December 2025 - July 2026 (26 weeks)
What was the ratio’s for design?
Net to gross = 10,670 (NIA) / 13,392m2 (GIA) / = 80%
How did you ensure that the client was protected from sub-contractors going into administration?
What is CLT?
CLT is a subcategory of engineered wood panel product made from gluing together at least 3 layers of solid-sawn lumber.
What are the benefits of using this material over another?
What are the negatives of using CLT?
Why did the client go with a direct award when funding was a concern?
The synergies of using BAM.
Already familiar with the building, previous good working relationship with the contractor, constructed sister scheme in Sheffield.
What did you do as part of managing the tender process?
What is CAT A? What is CAT B? What is CAT A+?