Procurement & Tendering Flashcards

(46 cards)

1
Q

What are single, two stage and negotiated tenders?

A

A single stage tender is when a client issues a tender for the whole of the project, with all the relevant information provided at the point of issue.

A two stage tender is where a contractor is appointed over two phases. There is an information phase first, allowing the contractor and client to collaborate, in which the contractor submits details under a pre-construction agreement and includes aspects regarding project preliminaries, method statements, design, overheads, and profit. The second phase is where the contractor will carry out the main works once the design has been sufficiently developed.

A negotiated tender is when a client invites one contractor to tender for the works, usually based upon an existing relationship, and they submit a price. Any queries are discussed and a figure is agreed upon.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are 5 changes as a result of the public procurement act?

A
  • Brought four regims (Public Contracts 2015, Utilities, Defence, Concession Regulations) under one act.
  • In an aim to improve VfM, more information will need to be shared publicly about procurements in the form of KPI’s and supplier performance.
  • Strict payment terms requiring any sum to be paid within 30 days enforced into contracts (with certain exceptions)
  • Introduction of a new oversight body to identify any areas of systemic failure within public bodies and procurement procedures, giving them investigative powers and make recommendations following.
  • A legal duty will now be placed on authorities to consider dividing large contracts into lots. This aims to increase competition and encourage greater involvement from SME organisations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why was the public procurement act introduced?

A

It was introduced to support a more competitive, flexible procedure, allowing for easier negotiation and partnership with public sector bodies, and increasing opportunities for small businesses and social enterprises.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can you give me an example of a rule introduced by the public procurement rule?

A
  • Payment terms of 30 days have been enforced into all contracts with limited exceptions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What do the guidance notes - ‘Developing a procurement strategy’ and ‘E-tendering’ say?

A

The DaCP guidance note covers selecting the appropriate procurement route based on the particular project’s characteristics.

E-tendering covers all things related to tendering electronically.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What procurement routes are you aware of?

A

Traditional - the client completes the design before tendering the works as a whole to a contractor for a price.

Design and build - the contractor is responsible for at least some of / the whole design as well as the construction works.

Management Contracting - the client appoints a management contractor who is responsible for organising trade packages to complete the works.

Construction management - the client hires a construction manager who coordinates the trade packages, but client retains the contractual link to sub-contractors and thus the risk for their performance.

Partnering - A collaborative approach where the client, contractor and other stakeholders work together to achieve shared goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Benefits of traditional over D&B?

A
  • Greater cost transparency due to fact design is finished and bids can be compared on a like for like basis.
  • Greater control over design.
  • Greater risk management as all design issues can be resolved before construction begins.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Benefits of management contracting over construction management?

A
  • In MC, client transfers the risk of subcontractor performance to the management contractor.
  • In MC, less contract admin to manage as just one contract between them and the MC.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is electronic tendering and what are some of the pro’s and con’s?

A

E-tendering replaces traditional paper-based methods with digital platforms, making the process more efficient and reducing paperwork.

Pro’s:

  • Efficiency - automates a lot of manual tasks, all in one place.
  • Transparency - clear audit trail.
  • Ease of use - the streamlined process makes it easier for bidders to access documents, submit bids, and track progress.

Con’s:

  • Requires initial investment and employee training to manage software.
  • System reliability - Dependence on technology means that system crashes or errors can delay the tendering process.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What measures would you take to ensure security in e-tendering?

A

E-tendering platforms often include security features such as encryption and e-signatures to protect sensitive information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a fair and comprehensive tender?

A

A fair and comprehensive tender is one that ensures all potential suppliers or contractors have an equal opportunity to bid and that the selection process is transparent and objective.

Clear Requirements: The tender documents should clearly outline the project’s scope, requirements, and evaluation criteria to avoid any ambiguity.
Equal Opportunity: All potential bidders should have access to the same information and be given equal time to prepare and submit their bids.
Transparent Process: The evaluation process should be transparent, with clear criteria and weightings that are communicated to all bidders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Where only 2 tenderers applied, how did you ensure value for money was achieved?

A

I compared the returns against benchmark data to ensure it was in line. Where I didn’t think it was an accurate representation of the market, I would ask the package to be re-tendered, and would offer additional suppliers to send the ITT where appropriate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you ensure value for money in the tender process?

A
  • Competitive tender process.
  • Receiving enough bids.
  • Compare against benchmark data.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What other prelims items did you pick up on when assessing the BQ’s against the drawings on the LRA?

A
  • MEWP’s had been priced by both MC and sub-contractor.
  • Scaffolding had been allowed for by both.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What packages were included in the external envelope that had been tendered by the same contractor on the LRA?

A
  • Brickwork and blockwork.
  • Cladding systems.
  • Steel framing systems.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What was the discount you negotiated with the contractor on the external packages?

A
  • £175,000.
  • Items such as waste management, site management, OHP etc were reduced.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Why do the risks increase from having one subcontractor carrying out several packages?

A

It increases the risk due to the fact that one sub-contractor is now responsible for several packages, a large portion of the value of the works and programme. If they were to go into administration it would have a greater effect than if they were just tendering for one package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What does a comprehensive credit check look like? How was this carried out?

A

I asked the contractor to carry one out, this involved them using the company ‘CreditSafe’ to gain a comprehensive report. This checks the following:

  • Adverse legal information
  • Director details
  • Up to five years of accounts
  • Company identity
  • Payment history
  • Credit limits and ratings
  • Holding and subsidiary companies
  • Image documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How would you analyse a tender?

A
  • I would check for clear arithmetical errors.
  • I would then check for any obvious errors in programme or onerous exclusions that would render the tender null and void (i.e. if it was a combined tender for the M&E works and they had excluded all mechanical works).
  • Post tender queries if any ambiguity with a tender (ensuring that they are worded so tenderers aren’t giving the chance to enhance their bid).
  • Normalisation process (stacking bids against each other, plugging in gaps) to show a comprehensive picture).
  • Post tender interviews if necessary (to discuss queries such as construction methodology in depth).
20
Q

What are the risks of too much normalisation of a tender?

A

The risks of normalising a tender too much is it risks:

  • Not giving a fair reflection of the price.
  • Potentially eliminating the competitive advantage of one tender over another.
21
Q

What was the procurement process like for selecting a school, i.e. Wings Academy or LRA?

A

Both used the SCF.

22
Q

How did you go about writing a tender report? What was included?

A

I used the standard Mace template.

This is split into the following headings:

Commentary - purpose of report.
Bid Timeline - iTT, Tender pack issue, time for return, receipt of returns, post tender queries, normalisation etc.
Summary of tenders, including pre and post normalisation amounts, review of exclusions/inclusions, programme, insurances/PCG/bonds.
Assessment according to the tender criteria.

23
Q

What is a framework? What are the benefits?

A

A procurement framework is a structured agreement that allows organizations, particularly in the public sector, to purchase goods, services, or works from pre-approved suppliers without needing to conduct a full tender process each time.

Benefits of frameworks include:

  • Helps to develop strong relationships.
  • Time saving.
  • Rates can be agreed upfront, leading to greater transparency.
24
Q

You state with regards to a schools project that several packages relating to the external envelope was tendered by the same subcontractor, negotiating a discount on the prelims. Did you consider negotiating a discount on the works costs also?

A

I reviewed the rates and found to be in line with the benchmark figures, so i didn’t want to jeopardize the contractor’s margin or the relationship by pushing on fair and equitable market rates.

25
What are the benefits and risks of having the same contractor responsible for several packages?
Benefits - economies of scale, one point of responsibility. Disadvantages - greater impact on project if they went into administration.
26
You state that with regards to Bank Project that you produced a tender report, can you please advise what was included in the tender report?
- Intro and scope of project. - Timeline of tender - when was received, clarifications, exclusions and inclusions, pre-normalised and post normalised figures. - Evaluation process - scoring criteria. - Recommendations and residual risks/mitigation.
27
You state with regards to a Bank Project that one of the tenderers had not included an incumbent subcontractor's costs. What are the pro's and con's of an incumbent on a project?
Pro's - Usually good existing relationships, well known supply chain, lower design related risks. Con's - less competition on pricing, resistance to change as they may want to keep constructing in the same fashion, complacency in not needing to improve service or look to be innovative.
28
What are the 4 core objectives of the Procurement Act 2023?
- Value for money. - Maximising public benefit. - Transparency. - Access for all suppliers
29
How does risk govern procurement route selection?
- Allocation of risks on a contractual level, as client appetite is huge in determining route. - Market conditions - huge levels of inflation might lead client to more risk averse route.
30
You state regarding a school project that you worked on that you ensured the client was receiving value for money - can you please advise what value is?
Value is subjective, but it is usually considered the ratio between benefit and the cost or effort required to achieve it.
31
On the same schools project you state that you undertook checks of drawings against the BoQ's received from the Contractor. Were these spot checks or were they detailed checks?
They were spot checks to start with, if quants didn't align then it would become a more detailed check.
32
When reviewing tender packages, do you review the MEP packages?
On this school project, I didn't review MEP packages.
33
How did you negotiate a discount in overall prelims where the same subcontractor was proposed for packages on the school project?
I raised it with the MC following the tender returns, so that they were able to issue as a tender query to all tenderers that where tendering.
34
What was the saving in the cladding package as a result of switching from a Kalzip to a Euroclad product?
£80k.
35
On Project X, why did you recommend design and build? What other procurement routes could you have taken?
Traditional with CDP: + Client can transfer the design risk for the most complex items with the contractor + Increase overall cost certainty of the scheme. - Slower procurement process and client still retains some design risk. Construction Management: + Speedy procurement process and a shorter construction time frame. - Client retains risk for design.
36
On the unnamed bank project, what did the scoring criteria look like?
1. Technical Capability was 60% which was made up of: - Experience in Similar Projects - Methodology and Approach - Compliance with Specifications - Programme and Delivery - Health and Safety Plan - Comprehensive risk assessments and mitigation strategies for working in a live environment. - Security Measures -Robust procedures to ensure the safety of bank assets, staff, and customers during the fitout. 3. Cost (40%) Price Competitiveness (40%): Overall cost of the project, ensuring value for money.
37
On the unnamed bank project, what would have been the consequence of a bidder excluding the BMS integration cost?
If missed, the client would have been liable for the cost as it had been excluded from their bid. So they may have selected the lowest tenderer, only to find out it wasn't actually the lowest once the BMS integration costs were added back in.
38
What docs would you issue in a single stage design and build tender?
- Drawings - Specs - Prelims document - Pre construction information pack - Employers requirements - Client's standard form of contract & amendments - Indicative programme length - Tender instructions - Scoring criteria
39
What are things you would see on a PQQ?
Financial Stability - Turnover, directors, solvency, credit history. Technical Capabilities - Bidder's expertise, equipment, resources, certificates Experience - Track record and past experience in similar projects Legal check - any pending suits etc. References - from previous clients or partners.
40
What is the definition of procurement? What is the definition of tendering?
Procurement is the overall act of obtaining goods and services from external sources and includes deciding the strategy on how these goods are to be acquired by reviewing the client's requirements and their attitude to risk. Tendering is an important phase in the procurement strategy. It is the bidding process to obtain a price and how a contractor is actually appointed.
41
On LRA - what specific criteria did you use to determine that the tender process was equitable and demonstrated value for money?
The second phase open book protocol. Ensuring contractor's bills were checked before issuing to market. Ensuring contractor went to three subcontractors, including client nominated ones. Ensuring normalisation was carried out properly, checking for duplication and plugged items were correct.
42
On project X, what risks did you identify with the design and build approach, and how did you advise the client to mitigate them?
I advised the client that the main risk was the quality of design due to it being the responsibility of the contractor. I advised the client to provide detailed ER's and to retain the design staff as TA's to ensure compliance.
43
What did you consider in your procurement report?
Intro Context on the project and client - including time available, appetite to risk, budget and desire for cost certainty, complexity of the project including specialist input required. Two most suitable routes - D&B and Traditional with CDP Recommendation and residual risks.
44
How do you advise on the correct procurement route?
- Establish the client's objectives and their appetite to risk. So running through - Funding - total funds and readiness. - Time - required completion date. - Performance of final product - this advises on quality required. Risk - likely impact to the client organisation of risks inherent in the project. Type of project - nature of the project may influence the project.
45
Why did you recommend D&B route on project X?
- Client organisation was relatively inexperienced, could benefit from early contractor involvement and transferring risk to the contractor. - Time frames for procurement and construction were limited so lent itself to D&B also.
46
On the unnamed bank project, how did you deal with qualifications that the bidders submitted?
Qualifications were reviewed initially to ensure compliance. If non-compliant, tenderers were given the opportunity to withdraw in order to produce a compliant tender.