What are single, two stage and negotiated tenders?
A single stage tender is when a client issues a tender for the whole of the project, with all the relevant information provided at the point of issue.
A two stage tender is where a contractor is appointed over two phases. There is an information phase first, allowing the contractor and client to collaborate, in which the contractor submits details under a pre-construction agreement and includes aspects regarding project preliminaries, method statements, design, overheads, and profit. The second phase is where the contractor will carry out the main works once the design has been sufficiently developed.
A negotiated tender is when a client invites one contractor to tender for the works, usually based upon an existing relationship, and they submit a price. Any queries are discussed and a figure is agreed upon.
What are 5 changes as a result of the public procurement act?
Why was the public procurement act introduced?
It was introduced to support a more competitive, flexible procedure, allowing for easier negotiation and partnership with public sector bodies, and increasing opportunities for small businesses and social enterprises.
Can you give me an example of a rule introduced by the public procurement rule?
What do the guidance notes - ‘Developing a procurement strategy’ and ‘E-tendering’ say?
The DaCP guidance note covers selecting the appropriate procurement route based on the particular project’s characteristics.
E-tendering covers all things related to tendering electronically.
What procurement routes are you aware of?
Traditional - the client completes the design before tendering the works as a whole to a contractor for a price.
Design and build - the contractor is responsible for at least some of / the whole design as well as the construction works.
Management Contracting - the client appoints a management contractor who is responsible for organising trade packages to complete the works.
Construction management - the client hires a construction manager who coordinates the trade packages, but client retains the contractual link to sub-contractors and thus the risk for their performance.
Partnering - A collaborative approach where the client, contractor and other stakeholders work together to achieve shared goals.
Benefits of traditional over D&B?
Benefits of management contracting over construction management?
What is electronic tendering and what are some of the pro’s and con’s?
E-tendering replaces traditional paper-based methods with digital platforms, making the process more efficient and reducing paperwork.
Pro’s:
Con’s:
What measures would you take to ensure security in e-tendering?
E-tendering platforms often include security features such as encryption and e-signatures to protect sensitive information.
What is a fair and comprehensive tender?
A fair and comprehensive tender is one that ensures all potential suppliers or contractors have an equal opportunity to bid and that the selection process is transparent and objective.
Clear Requirements: The tender documents should clearly outline the project’s scope, requirements, and evaluation criteria to avoid any ambiguity.
Equal Opportunity: All potential bidders should have access to the same information and be given equal time to prepare and submit their bids.
Transparent Process: The evaluation process should be transparent, with clear criteria and weightings that are communicated to all bidders.
Where only 2 tenderers applied, how did you ensure value for money was achieved?
I compared the returns against benchmark data to ensure it was in line. Where I didn’t think it was an accurate representation of the market, I would ask the package to be re-tendered, and would offer additional suppliers to send the ITT where appropriate.
How do you ensure value for money in the tender process?
What other prelims items did you pick up on when assessing the BQ’s against the drawings on the LRA?
What packages were included in the external envelope that had been tendered by the same contractor on the LRA?
What was the discount you negotiated with the contractor on the external packages?
Why do the risks increase from having one subcontractor carrying out several packages?
It increases the risk due to the fact that one sub-contractor is now responsible for several packages, a large portion of the value of the works and programme. If they were to go into administration it would have a greater effect than if they were just tendering for one package.
What does a comprehensive credit check look like? How was this carried out?
I asked the contractor to carry one out, this involved them using the company ‘CreditSafe’ to gain a comprehensive report. This checks the following:
How would you analyse a tender?
What are the risks of too much normalisation of a tender?
The risks of normalising a tender too much is it risks:
What was the procurement process like for selecting a school, i.e. Wings Academy or LRA?
Both used the SCF.
How did you go about writing a tender report? What was included?
I used the standard Mace template.
This is split into the following headings:
Commentary - purpose of report.
Bid Timeline - iTT, Tender pack issue, time for return, receipt of returns, post tender queries, normalisation etc.
Summary of tenders, including pre and post normalisation amounts, review of exclusions/inclusions, programme, insurances/PCG/bonds.
Assessment according to the tender criteria.
What is a framework? What are the benefits?
A procurement framework is a structured agreement that allows organizations, particularly in the public sector, to purchase goods, services, or works from pre-approved suppliers without needing to conduct a full tender process each time.
Benefits of frameworks include:
You state with regards to a schools project that several packages relating to the external envelope was tendered by the same subcontractor, negotiating a discount on the prelims. Did you consider negotiating a discount on the works costs also?
I reviewed the rates and found to be in line with the benchmark figures, so i didn’t want to jeopardize the contractor’s margin or the relationship by pushing on fair and equitable market rates.