In your go to webinar you talk about defining repudiation and termination under a JCT D&B contract? What are these?
Termination under a JCT contract is the ending of a contract. It can be done by the employer, the contractor or mutual consent by both parties.
Repudiation of a contract is when one party renounces their obligations under a contract, either expressly or by conduct.
What are listed items under JCT?
Listed items under a JCT contract are the goods, plants and materials to be purchased. These can be paid for off-site provided certain conditions are met, i.e. vesting agreement, set aside from other materials and clearly marked, a surety bond if necessary.
What are the implications of listed items under JCT contracts?
Listed items are important as the contractor will be entitled to payment for these while they are stored offsite (i.e. prior to incorporation into the works) provided that certain conditions have been met.
What conditions have to be met for listed items for them to be paid in an interim payment?
What are the key changes to JCT in the 2024 updates?
What are the consequences of a contractor becoming insolvent under a JCT contract?
In the event that the contractor becomes insolvent, the employer may at any time, by notice to the contractor, terminate its employment.
Under JCT forms of contract, the contractor’s obligation to carry out the works is automatically suspended.
As with the automatic suspension of the work, the employer’s obligation to pay the contractor is automatically suspended until the agreement and issue of a final account. This payment obligation comes into force regardless of whether the employer issues a notice of termination.
How can an employer terminate a contract under JCT D&B?
An employer can terminate a contract if:
What are the consequences of an employer terminating a JCT D&B contract?
What is the consequence of a contractor becoming insolvent under a JCT D&B contract?
An employer can terminate the contractor’s employment.
The employer can then stop payment and take possession of the site, including using any plant, materials or equipment.
How does the overall payment process works under JCT D&B 16?
Payments under JCT D&B can be either stage payments which are detailed in the contract, or interim payments which are assessed based upon the works done on site and the pricing document.
The payment process starts with the:
INTERIM VALUATION DATE -> 7 days later -> DUE DATE -> 14 days later -> FINAL DAY FOR PAYMENT.
Give me 3 examples of X clauses within a NEC4 contract and how they work?
X4 - Ultimate Holding Company Guarantee (essentially a parent company guarantee to uphold the contract if the subsidiary company defaults)
X11 - Termination by Client (allows client to terminate at will, providing a strcutred payment process to the contractor to ensure they are paid for all works done to date).
What building.com articles have you read recently?
The improvement of the BSR from July, shifting from being under the HSE to the Ministry of Housing, Communities and Local Government (MHCLG).
This has seen changes like communicating during application stage, engaging private registered building control inspectors, issuing provisional approvals with conditions similar to planning.