A contract is considered physically complete when the contractor has completed all the required deliveries and:
a. All obligated funds on the contract have been expensed.
b. The contractor has submitted their final invoice.
c. The Government has inspected all the items.
d. The Government has accepted all the items.
d. The Government has accepted all the items.
Contract files for contracts using simplified acquisition procedures should be considered closed when the contracting officer receives evidence of two things. The first is receipt of the property or service. What is the second?
a. Final acceptance
b. Final inspection
c. Final payment
d. Final approval of the Contractor Performance Assessment Reporting System (CPARS) report
c. Final payment
What office/entity is responsible for initiating administrative closeout of the contract after receiving evidence of physical completion?
a. The contractor
b. The Government contract administration office
c. The Government user/requiring activity
d. Defense Contract Audit Agency (DCAA)
b. The Government contract administration office
The contracting officer is responsible for initiating contract closeout procedures after the contracting officer receives:
a. A final audit from the Inspector General
-b. A written request for contract closeout from the contractor
c. Notice that the last item has been delivered
d. Evidence of physical completion
d. Evidence of physical completion
You are a contracting officer who has a $260,000 commercial contract. You decide you need to terminate the contract because the contractor has failed to perform. What is the name of this type of termination?
a. For Noncompliance
b. For Cause
c. For Default
d. For Failure
b. For Cause
What part of the FAR covers terminations?
a. FAR part 46
b. FAR part 47
c. FAR part 48
d. FAR part 49
d. FAR part 49
You’ve received a claim on your contract. The contractor is required to certify its claim above what amount?
a. $100,000
b. $10,000
c. $10 million
d. $100 million
a. $100,000
What entity can the contractor appeal to if they do not agree with the contracting officer’s final decision on a claim?
a. The head of the agency
b. The head of the contracting activity (HCA)
c. The United States Court of Federal Claims
d. The General Accountability Office (GAO)
c. The United States Court of Federal Claims
When shall contracting officers negotiate equitable adjustments resulting from change orders?
a. Within 30 days
b. Within 90 days
c. Within the shortest practicable time
d. Within a time frame that is acceptable to the contractor
c. Within the shortest practicable time
Who may execute contract modifications on behalf of the Government?
a. Contracting officers
b. Contract specialists
c. Contracting officer’s representatives (COR)
d. Program managers
a. Contracting officers
Which of the following modifications must be issued bilaterally?
a. Making administrative changes
b. Making a negotiated equitable adjustment caused by a change order
c. Issuing a change order
d. Issuing a termination notice
b. Making a negotiated equitable adjustment caused by a change order
What are the two types of contract modifications?
a. Supplemental and termination
b. Supplemental and equitable adjustment
c. Termination and unilateral
d. Unilateral and bilateral
d. Unilateral and bilateral
Which of the following contract modifications must be signed by both the contractor and the contracting officer?
a. An administrative change
b. A termination notice
c. An agreement definitizing a letter contract
d. Exercising an option within the scope of the contract
c. An agreement definitizing a letter contract
Change orders issued under the changes clause of the contract use which form?
a. SF 30
b. SF 33
c. SF 44
d. SF 1449
a. SF 30
Which FAR part is titled “Subcontracting Policies and Procedures”?
a. FAR part 43
b. FAR part 44
c. FAR part 45
d. FAR part 46
b. FAR part 44
Which of the following entities has privity with a first-tier subcontractor?
a. The contracting officer
b. The prime contractor
c. The Defense Contract Management Agency (DCMA)
a. The Defense Contract Audit Agency (DCAA)
b. The prime contractor
Does the Government’s policy to require prime contractors to incorporate, to the maximum extent practicable, commercial items or nondevelopmental items as components of items supplied to the agency, apply to subcontractors at all levels?
a. No, it only applies to first-tier subcontracts.
b. No, it only applies to first- and second-tier subcontracts.
c. Yes.
d. The policy of flowing down this requirement no longer applies to DoD acquisitions.
c. Yes.
Which of the following statements regarding Small Business Subcontracting Plans is accurate?
a. Required for contracts with large businesses, regardless of location
b. Required for contracts with both large and small businesses, regardless of location
c. Not required for contracts with large or small businesses, regardless of location
d. Not required for contracts with large businesses performed overseas
d. Not required for contracts with large businesses performed overseas
Quality assurance on contract actions valued below the simplified acquisition threshold (SAT) is:
a. Minimal, unless a special circumstance exists
b. The same as above the SAT
c. More stringent for commercial items
d. Not necessary, as risk of loss is considered too low to justify the expense
a. Minimal, unless a special circumstance exists
When preparing a solicitation, the quality requirements essential to ensure the integrity of the supplies or services is developed by whom?
a. The procurement contracting officer (PCO)
b. The activity responsible for technical requirements
c. The contractor’s quality control representative
d. The administrative contracting officer (ACO)
b. The activity responsible for technical requirements
According to the FAR, acceptance of supplies or services is the responsibility of whom?
a. The project manager (or designated representative)
b. The quality assurance representative (QAR)
c. The contracting officer
d. The plant clearance officer
c. The contracting officer
In commercial contracting, what quality system is utilized?
a. The Government’s
b. The contractor’s
c. The Commercial Quality System (CQS)
d. ISO 900 Series
b. The contractor’s
When does title for a completed product transfer to the Government, assuming the product meets all contract requirements?
a. Title transfer only applies to real estate transactions, not purchases of products.
b. When the Government takes physical possession of the product
c. On the last day of the month that the item was presented for inspection and acceptance
d. Upon formal acceptance by the Government
d. Upon formal acceptance by the Government
Does the Government have the right to inspect a product before it is accepted?
a. No.
b. No, unless the item is a commercial product.
c. Yes, unless the item is a commercial product.
d. Yes, always.
d. Yes, always.