Conflict Avoidance Flashcards

(22 cards)

1
Q

What does ADR mean?

A

Alternative Dispute Resolution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the main methods of ADR?

A

Negotiation, Mediation, Conciliation, Adjudication, Arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is negotiation?

A

An informal discussion between parties with the intention of reaching a settlement without the matter being escalated to more formal proceedings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the pros and cons of negotiation?

A

Pros: Little to no cost, Quick, Easy; Cons: Can become hostile, Not guaranteed to settle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is mediation?

A

When a neutral third party “the mediator” facilitates the negotiation. Impartial and not allowed to give an opinion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the pros and cons of mediation?

A

Pros: Cheap when compared to other methods; Cons: Not guaranteed to settle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is conciliation?

A

The same as mediation, however the conciliator is able to offer their advice/opinion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is an adjudication?

A

Supposed to a faster way to settle than more formal proceedings. Common in construction. An adjudicator makes a decision for the parties. Standard time frames for all adjudications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the pros and cons of adjudication?

A

Pros: Under the construction act, both parties have the right to adjudicate at any point. Quick – decisions are made in 28 days. Cheaper than arbitration and litigation. Decisions binding; Cons: Rough Justice – rushed 28-day process. Parties bear their own legal costs. Not suited to complex disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is arbitration?

A

An independent arbitrator reviews the evidence and makes a decision that is final.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the pros and cons of arbitration?

A

Pros: Confidential unlike litigation. Despite being a formal proceeding, its informal compared to litigation. Arbitrator provides an end to the dispute; Cons: Expensive. No jury

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is litigation?

A

Formal court proceedings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the pros and cons of litigation?

A

Pros: Decision is final. Good for complex cases. Decision is enforceable by law; Cons: Very expensive. Public. Takes a lot of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the differences between arbitration and litigation?

A

Litigation takes place in a public court and take 6 months to 2 years. Arbitration is private. Litigation has judges and juries, whereas arbitration has an arbitrator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you avoid a dispute in the first place?

A

Circulate meeting minutes via email. Always record conversations via email. Keep records of things. Take lots of pictures. Follow RICS guidance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the HGCRA?

A

Legislation which applies to most construction contracts. Payment terms. Adjudication. Amended in 2011 by Local Democracy Economic Development and Construction Act

17
Q

Do all parties have the right to adjudicate including domestic clients?

A

Not domestic clients unless stated in contract

18
Q

When and what did LDEDCA change?

A
  1. Added payless notices. Ban pay-when-paid. Adjudication for oral contracts. Default payment notices
19
Q

What are the timescales of the adjudication process?

A

Notice for adjudication. 7 days for referral. 7 more days for a response. 14 days to reply. Decision made 28 days from the notice

20
Q

What is a final account?

A

Definitive financial statement to close an account. Final agreed sum of money. Have three months to agree from PC

21
Q

What were they disputing?

A

The housing authority put in a claim that the contractor was over charging for works complete. The contractor failed to substantiate for most works complete

22
Q

What is a scott schedule?

A

A summary document for assessments on a dispute which details Claim references, Assessment and claim values, Dates, Status, Comments