Contract Admin and Practice Flashcards

(58 cards)

1
Q

What is practical completion?

A

Practical completion is the date in which the contractor completes the works. Different from Completion Date which is the target date set in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How is a JCT Contract built up?

A

Agreement: Date of agreement, Employers details, Contractors details; Recitals: Intro, Works descriptions, Drawings, Pricing schedule; Articles: Names the parties, ADR, Obligations; Contract particulars: Retention, Liquidated damages, Insurance, Listed items; Attestation: Signatures, As a deed or underhand, Deed – 12 years limitation period, Underhand 6 years limitation period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the role of the Contract Administrator?

A

Manages the contract, Issues instructions, Reviews claim entitlement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is retention?

A

A portion of money set aside from each interim payment to act as an incentive for the contractor to return and rectify any defects during the defect period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a retention bond?

A

Financial guarantee that the client withholds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the defects period?

A

A period of 6-12 months where the contractor must return to rectify any defects as a result of their work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are my responsibilities as a QS at practical completion?

A

Agree final account, Apply for final interim payment cert, Apply for first release of retention.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the JCT payment cycle?

A

The due day is 7 days from the valuation date in the contract; Payment notice must be issued 5 days after the due date; 14 days from the due date the contractor is paid; No less than 5 days before the final date for payment a pay less notice is issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does a QS do at each key date?

A

Valuation date – submit application for payment; Due date – nothing; Payment notice date – issue payment notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a non-completion certificate?

A

Cert which states that a completion date has been missed. Gives rights for the client to levy liquidated damages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are liquidated damages?

A

Pre-determined estimate of loss.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the difference between liquidated and unliquidated damages?

A

Liquidated is pre-determined; Unliquidated is actual loss.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are listed items?

A

Items agreed to be paid upfront/offsite.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What was included in my vesting cert?

A

Unique reference, Description, Cost, Location, Picture and reference.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you submit an extension of time?

A

Issue a notice of delay; Issue an application for extension of time which includes: Details around the delay, Estimated duration, Relevant event clause.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you submit a loss and expense?

A

Give notice in writing that I intend to submit a loss and expense claim; State description; Relevant matter clause; Any substantiation required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Key differences between JCT and NEC?

A

Programme is a key element of an NEC contract whereas it is hardly mentioned under JCT; Variations / CEs; PM / CA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What advice do you provide internally in respect of delays due to weather?

A

Weather is a relevant event however not a relevant matter, meaning the Contractor will only receive time and no money. Although the extension of time covers the period in which the contractor will be exposed to LADs, the additional prelims will be at the contractors cost. I’d advise to explore other avenues of applying for extensions of time where loss and expense is also due.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What advice do you provide regarding the changes introduced in JCT 2024?

A

The contract now includes asbestos, contaminated materials and UXOs when discovered on site: I’d advise that employers should ensure investigations are carried out before tendering; Contractors should assess their entitlement to time and money. There is a mandatory good-faith collaboration clause now included: Requires parties to act in good faith.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What advice do you provide for S/C LAD rates?

A

LADs should be a pre-estimate of loss and not a penalty; The rates should be tailored to the subcontractor’s scope; Avoid using massive rates for small scale subcontracted works as they will become unenforceable; I advise to proportion the rates based on the scale and how critical the work is.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How did I prepare the loss and expense claim for prolongation at 75 London Wall?

A

Issue a delay notice: Quote the relevant matter, Detail the delay, Give notice that I am planning on submitting a loss and expense claim; Prepared the claim: Used invoices, Time sheets, Site diaries, Based on actual cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is included in LAD calculations?

A

Loss of revenue, Offsite storage, Legal fees, Consultant fees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How do JCT subcontracts provide for LADs?

A

There is no clause for LADs in a subcontract; They are structured to be back to back with main contract; If they are to be adjusted, I would need to arrange for the subcontract to be amended.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Under which circumstances would you recommend using JCT D&B?

A

When the Employer wants to maximise buildability; When the employer doesn’t want design responsibility; When the employer wants a quick start on site.

25
What are the benefits to a contractor of a D&B contract?
Factor in a risk premium into their price; Opportunities when building the project by utilising different materials or methods of construction that still meet the Employers requirements; For example, as the Contractor holds design responsibility, they can carry out value engineering exercises within the design.
26
Which entity would usually complete RIBA Stage 4 on a DB contract?
The Contractor would usually hold the design responsibility at stage 4 on a D&B contract.
27
Is DB appropriate if the design was completed to RIBA Stage 4?
No, a traditional approach would be more suitable as the design is already at the responsibility of the Employer; Another benefit of D&B is a quick start on site, however that will not matter if the design is already complete.
28
Would you recommend the use of letters of intent?
No I would not advise the use of letters of intents; They would be a last resort; They are generally used for enabling early works packages, however they carry significant risk; They must be completed with caution ensuring that they contain a defined scope, costs, time limits etc; By the time you have drafted a secure letter of intent, you may as well have drafted a contract.
29
What are the risks when using a LOI?
Legal uncertainty; Disputes over scope; Financial exposure.
30
Do you produce LOI's?
No this should be carried out by a legal professional.
31
What is a Collateral Warranty and when is it appropriate to use?
A collateral warranty provides a contractual link between two parties involved in the same project, however would not usually have a contractual link; For example, I used a collateral warranty at 63 new bond street for the piling as it was designed by our subcontractor. This provided security and insurance for the Employer.
32
What is a key consideration when including payment schedules in Subcontracts?
Ensure the payment schedule is aligned with the main contract; Ensure there are enough periods listed to cover the duration of the subcontractor’s scope.
33
What happens if the dates expire in the payment schedule?
There should be a note that they continue in the same cycle; Contractually, it would signify the final valuation.
34
What do you need to form a contract?
Offer, Acceptance, Intent, consideration.
35
What are some differences between JCT and NEC contracts?
PM / CA; Compensation events must be implemented; Variations are not agreed until final account.
36
How are JCT contract structured?
Agreement: Project name, Employer, Contractor; Recitals: Introduction, Description fo work, Pricing schedule; Articles: ADR, Obligations; Contract particulars: Retention, Liquidated damages, Insurances.
37
What are JCT approximate quants?
Remeasured.
38
What is the HGCRA?
Construction act; Forms part of every construction contract; Provides rights around payment and disputes.
39
What is LDEDCA?
Amended the HGCRA; Added payless notices; Removed pay when paid; Added oral contracts.
40
What is an advance payment bond?
Upfront payment with a guarantee that works will be complete; Protects the client if the contractor breaches contract.
41
Name some examples of relevant events?
Exceptionally adverse weather; Variations; Force majeure; Third party disruptions.
42
Name some examples of relevant matters?
Possession failure; Variations; Disruption.
43
Why would you advise to use a JCT minor works contract?
Small scale; Low risk; Low value.
44
What are the insurance options under a JCT?
Option A (Contractor Insures) – The Contractor takes out a joint names policy; Option B (Employer Insures) – The Employer takes out a joint names policy; Option C (Existing Structures / Refurb) – The Employer insures the existing structures and contents and the new works.
45
What is a joint names policy?
Construction insurances that cover both Employer and Contractor under a single policy; It ensures they are treated as one entity regarding claims; Covers both the existing structure and the contract works.
46
What is public liability?
Covers injury or damage to third parties; Example – falling debris on the public footpath.
47
What is Employers liability?
Covers injury or damage to contractors’ own staff; Example – health and safety incident.
48
What is Professional Indemnity Insurance?
Protection for professional negligence; Example – design errors.
49
What are the required PI levels?
£100k or less turn over - £250k; £100k to £200k - £500k; Above £200k - £1m.
50
What is subrogation in insurance?
Insurance principle allowing insurers to step into the shoes of a policy holder to sue a third party; Example – the insurer steps into the main contractors shoes to sue a subcontractor.
51
What are third party rights?
Allows a person not directly party to a contract to enforce its terms.
52
What is the difference between third party rights and collateral warranty?
Collateral warranty has a separate document; Third party rights are more loose.
53
What happens at PC?
The Contractor finishes their scope; The CA issues a certificate of practical completion; The first half of retention is released; The defect liability period starts.
54
What is the payment cycle under JCT?
The valuation date is stipulated in the contract; The due date is 7 days after the valuation date; The payment notice is then issued 5 days after the due date; The final date for payment is 14 days after the due date; And a pay less notice must be served 5 days prior to the final date for payment.
55
What did HGCRA introduce?
Rights to adjudicate; Interim payments; Right to suspend performance for non-payment.
56
What did LDEDCA introduce?
Payless notices; Disallowed pay when paid; Oral contracts.
57
What steps must be taken before deducting liquidated damages?
The CA must serve a notice for non-completion; LADS will then be deducted through a payless notice.
58
Do materials to be paid off site need to be agreed pre-contract?
No it is discretionary from the Employer and should be recorded in a vesting certificate.