What is practical completion?
Practical completion is the date in which the contractor completes the works. Different from Completion Date which is the target date set in the contract.
How is a JCT Contract built up?
Agreement: Date of agreement, Employers details, Contractors details; Recitals: Intro, Works descriptions, Drawings, Pricing schedule; Articles: Names the parties, ADR, Obligations; Contract particulars: Retention, Liquidated damages, Insurance, Listed items; Attestation: Signatures, As a deed or underhand, Deed – 12 years limitation period, Underhand 6 years limitation period.
What is the role of the Contract Administrator?
Manages the contract, Issues instructions, Reviews claim entitlement.
What is retention?
A portion of money set aside from each interim payment to act as an incentive for the contractor to return and rectify any defects during the defect period.
What is a retention bond?
Financial guarantee that the client withholds.
What is the defects period?
A period of 6-12 months where the contractor must return to rectify any defects as a result of their work.
What are my responsibilities as a QS at practical completion?
Agree final account, Apply for final interim payment cert, Apply for first release of retention.
What is the JCT payment cycle?
The due day is 7 days from the valuation date in the contract; Payment notice must be issued 5 days after the due date; 14 days from the due date the contractor is paid; No less than 5 days before the final date for payment a pay less notice is issued.
What does a QS do at each key date?
Valuation date – submit application for payment; Due date – nothing; Payment notice date – issue payment notice.
What is a non-completion certificate?
Cert which states that a completion date has been missed. Gives rights for the client to levy liquidated damages.
What are liquidated damages?
Pre-determined estimate of loss.
What are the difference between liquidated and unliquidated damages?
Liquidated is pre-determined; Unliquidated is actual loss.
What are listed items?
Items agreed to be paid upfront/offsite.
What was included in my vesting cert?
Unique reference, Description, Cost, Location, Picture and reference.
How do you submit an extension of time?
Issue a notice of delay; Issue an application for extension of time which includes: Details around the delay, Estimated duration, Relevant event clause.
How do you submit a loss and expense?
Give notice in writing that I intend to submit a loss and expense claim; State description; Relevant matter clause; Any substantiation required.
Key differences between JCT and NEC?
Programme is a key element of an NEC contract whereas it is hardly mentioned under JCT; Variations / CEs; PM / CA.
What advice do you provide internally in respect of delays due to weather?
Weather is a relevant event however not a relevant matter, meaning the Contractor will only receive time and no money. Although the extension of time covers the period in which the contractor will be exposed to LADs, the additional prelims will be at the contractors cost. I’d advise to explore other avenues of applying for extensions of time where loss and expense is also due.
What advice do you provide regarding the changes introduced in JCT 2024?
The contract now includes asbestos, contaminated materials and UXOs when discovered on site: I’d advise that employers should ensure investigations are carried out before tendering; Contractors should assess their entitlement to time and money. There is a mandatory good-faith collaboration clause now included: Requires parties to act in good faith.
What advice do you provide for S/C LAD rates?
LADs should be a pre-estimate of loss and not a penalty; The rates should be tailored to the subcontractor’s scope; Avoid using massive rates for small scale subcontracted works as they will become unenforceable; I advise to proportion the rates based on the scale and how critical the work is.
How did I prepare the loss and expense claim for prolongation at 75 London Wall?
Issue a delay notice: Quote the relevant matter, Detail the delay, Give notice that I am planning on submitting a loss and expense claim; Prepared the claim: Used invoices, Time sheets, Site diaries, Based on actual cost.
What is included in LAD calculations?
Loss of revenue, Offsite storage, Legal fees, Consultant fees.
How do JCT subcontracts provide for LADs?
There is no clause for LADs in a subcontract; They are structured to be back to back with main contract; If they are to be adjusted, I would need to arrange for the subcontract to be amended.
Under which circumstances would you recommend using JCT D&B?
When the Employer wants to maximise buildability; When the employer doesn’t want design responsibility; When the employer wants a quick start on site.