What is a Building Approval?
What is the role of the architect under the construction contract?
Who certifies building at completion and performs a final check? Who undertakes the fire commission check? When are you totally finished?
What does the building certifier need for a building approval?
What is Operational Works
Council infrastructure to be provided by the contract in order to fulfil the DA & BA as per the authority’s requirements.
Before work on site, builder needs?
Before make first progress payment the contractor must ?
Under the terms of the ABIC contract the contractor is required to produce a program showing how the works will be completed. Should this program become part of the contract documents?
You have received the first progress claim from the contractor and it appears that he is front loading the contract and over claiming on the project. What can you do?
If the builder is claiming for products ordered but not on site can you approve the claim?
What can a subcontractor do if they are not paid by the head contractor ?
What are Prime Costs & Provisional Sums?
Provisional Sum:
Prime Cost Sum:
What are the risks with using either prime cost and/or provisional sum?
In an ABIC contract what is the procedure to be followed when using prime cost and/or provisional sums?
What power does the architect have In giving instructions on Latent Defects?
When excavating, the contractor uncovers a footing of the adjacent site’s heritage building – how do you proceed?
If a safety issue occurs on site, what do you do?
When assessing a progress claim from the contractor, what must you take account of?
What happens if owner takes possession early?
You have notified the contractor and he is refusing to come to site and rectify defects during DLP. What do you do?
Pedestrian has been injured adjacent to site. What do you do?
How is practical completion determined ?
What happens at Final Certificate?
What happens if there is a disagreement between the parties to a building contract? What happens if the dispute can’t be resolved?