What types of tenders are there ?
What is an open tender ?
What is a negotiated tender ?
What is a selective tender ?
what is a pre-registration / pre-qualification tender ?
In the code of tendering what are some of the principal’s obligations ?
What needs to go into a tender package for tendering contractors?
Notice to tenderers - Provides the information tenderers require to prepare and lodge a tender.
Conditions of Tendering - outlines information that should accompany the tender, the details for lodging tenders and the matters that will be taken into account when considering tenders.
General Conditions of Contract - If standard form contract to be used not included. Just advice on how to obtain.
Contract Schedules - Critical. All contract schedules or appendices completed except for items to be submitted by tenderers.
Tender Form - To ensure that the tender is complete and that all the information necessary to review the tender is provided
Schedules of Monetary Sums - monetary sums, provisional sums, prime cost sums. Only if not included in the contract schedules.
Tender Schedules - To be completed by tenderer and could include current commitments, rates, relevant information on proposed ‘particular persons’.
Technical Specification - By specialist consultants.
Drawings - By specialist consultants.
BoQ - Bill of Quantites - if applicable.
What is included in the ‘notice to tender’s?
What is the purpose of conditions of tendering?
outlines information that should accompany the tender, the details for lodging tenders and the matters that will be taken into account when considering tenders.
What are Contract Schedules (annexures)?
Critical. All contract schedules or appendices completed except for items to be submitted by tenderers.
What are Tender Schedules?
What are Specification Schedules?
How will the tenders be assessed? Where to from there?
How do you form a selected list of prospective tenders?
The client’s cousin is a builder and client would like to use him as the contractor. What do you do?
The lowest tender comes in 25% less than the others. Can the client accept this tender?
What is a bill of quantities ?
What do you do when a tenderer notifies you of discrepancies in the tender documents?
What are tenderer’s options during negotiations ?
How long is a typical tender period ?
BOQ can reduce by around 5 weeks
What are the step of the tender process ?
What is the code of tendering ?
What are some of the tenderers obligations in the code of tendering?
What is a Makret-led proposal ?
Market-led proposals are proposals from the private sector that seek an exclusive commercial arrangement with government to deliver a service or infrastructure to meet a community need. They always include a role for government, such as providing access to government land, assets, information, or networks. In return, market-led proposals are expected to provide benefits to government and/or the Queensland community.