What is a Variation? What does it impact?
A change in:
Impacts:
Describe the process by which a variation and its effects are recorded & managed under the ABIC contract?
A variation is communicated and managed through written correspondence
Client requested variations after PC, not included in contract. What now?
How can the client be protected from site related claims?
If there are Errors or omissions on docs, what happens?
Who is responsible for a dilapidation Report?
Does a variation always cause an adjustment to the contract? Explain.
Every variation is a change to the contract (but not necessarily a change to cost or time)
Under the ABIC contract what is the difference between the term “variation” and a claim by the contractor to “adjust the contract”?
What is the contractor entitled to if there is a change to the contract price ?
Item 31 of Schedule 1 nominates an percentage of the value of the change which the contractor is entitled to. This is a percentage for the contractor’s overheads and profit (15% default).