What is nomination?
Selection of a particular subcontractor to carry out the works. Gives the client greater control over a particular section of work.
What is included in a contractors valuation?
Prelims, measured works, materials on site, variations, retention, any previous payments
What is required for a contract to be formed?
Offer - consideration - acceptance - intention to create legal relations
What are the main differences between the JCT contract suite and the NEC contract suite?
What is frustration?
Where an event beyond the control of either party makes it impossible or illegal to fulfil their contractual obligations.
What’s the difference between latent and patent defects?
Latent defects are not identifiable on inspection and only become apparent later down the line.
Patent defects are obvious and should be identified during a routine inspection.
What are the main sections of a JCT contract?
Recitals, articles, contract particulars, attestation, conditions, schedules.
What are the different forms of JCT contract?
Minor works
Intermediate
Standard Building Contract (with/without/approximate quantities)
Design & Build
Construction management
Major Projects
Prime Cost Building Contract
What are the main changes to the 2024 suite of JCT contracts?
What is an extension of time?
A contract provision for amendment of the practical completion date due to unforeseen circumstances.
What is loss and expense?
Additional costs incurred by the contractor as a result of the works progress being affected by a matter for which the client is responsible.
How are liquidated and ascertained damages calculated?
Calculated at the start of the project and inserted into the contract.
Should be based on what the likely genuine financial loss would be to the client if the project is not completed on time.
What must be in place before LADs can be deducted?
What is the timings process after receiving a contractors valuation?
The due date is 7 days after the valuation date. A payment notice must be issued within 5 days of the due date. The client must make payment to the contractor within 14 days of the due date.
What is meant by ‘time at large’?
There is no set completion date and the contractor only has an obligation to complete the works within a ‘reasonable time’.
What is a vesting certificate?
A legal document confirming the ownership of assets that have not been delivered to site.
What is a retention of title clause?
Where the sub contractor maintains ownership of materials until they are paid by the main contractor.
How do you evaluate a contractors valuation?
What is a collateral warranty?
A contract between the client and a third party (I.e. a subcontractor).
What is a retention bond?
A bond provided by the contractor in lieu of taking retention from interim payments.
What happens at practical completion?
What is the difference between partial possession and sectional completion?
Sectional completion is a contractual obligation for the contractor to hand over the section at the stated date. Partial possession relies on the contractors consent.
What is a performance bond?
Typically provided by banks or insurance companies and give the employer a guarantee of payment up to a certain amount should they suffer financial loss if the contractors breaches their obligations.
Taken out by the contractor and the premium for taking out the bond is added onto the contract sum.
What is the base date?
The date from which the conditions the tender was prepared under are considered to be known to the contractor so are reflected in their price.