What is the difference between a warranty and a bond?
Can the Client / Contractor terminate a contract if either party becomes insolvent?
Yes
What is change control?
A process that ensures potential changes to the deliverables of a project or the sequence of work in a project, are recorded, evaluated, authorised and managed
What is a variation?
Alterations or modifications to the design, quality or quantity of the contract works, to the site access or working conditions
Why might a Variation arise?
Can the contractor object to a variation?
In accordance with clause 13.1(a) of the Hong Kong Standard Building Contract yes.
How soon does a contractor have to comply with an instruction?
Forthwith
What can the Architect (PM) do if they don’t?
What are the valuation rules in the HKSBC?
There are three rules for measurable work:
What is quantum meruit?
Translates to ‘the amount deserved’. It is used to refer to a claim for a reasonable sum, such as when a contractor seeks payment for work which has not been determined by a contract.
Who can instruct change?
Depending on the form of contract. Standard form of contract it is typically the Architect, in my experience this role has been transferred to the Project Manager on behalf of the Client.
How do you price change?
I will work with my QS team using the rates agreed in the SOR
What is an Extension of Time (EOT)?
Adjustment to the completion date and relieves the contractor’s liability to pay liquidated damages for the period of the extension (Listed Events)
What clause within the HKSBC is the EOT Clause?
Clause 25
Does an EOT always give rise to additional money to the Contractor?
No
Why does an EOT not always qualify for additional money?
As the delay cause could be at no fault to either party (Force Majeure - Covid-19)
What is loss and Expense (L&E)?
Reimburses the contractor for direct loss and/or expense incurred in carrying out additional work or from an employer’s breach of contract (Qualifying Events)
What clause within the HKSBC is the L&E Clause?
Clause 27
What would qualify the contractor to be entitled to a L&E in the HKSBC?
The contract stipulates a list of Qualifying Events which the contractor is able to make a claim in respect of
What are the procedures for claiming loss and expense under the HKSBC?
The Contractor shall in writing and within 28 days of becoming apparent of an event may give rise to claim or within 7 days of receiving a claim from a NSC issue formal notice.
The Contractor should also as soon as practicable / within 60 days of giving the first notice submit the following:
If Contractor cannot provide this within the 60 day period a notice should be issued to the Architect (PM) to that effect and issue interim particulars
What are the procedures for claiming EOT under the HKSBC?
The contractor must first give a notice of delays in writing within 28 days of the commencement of likely delay that could cause delay to the completion date becoming apparent.
First Notice:
Second Notice:
How do you fix a new completion date?
After receipt of the contractors second notice, within 60 days of receipt providing the listed event is valid.
What are the basic requirements of Contractors All Risk Insurance?
Can you list out the contents page of the HKSBC