How do you get the client to buy into the milestones within the programme?
Regular reviews of the contract with the Client and explaining the cause and effects of decisions to the Contract.
Who owns programme float?
No clear rule – generally it belongs to the contractor
The contractor normally includes float in his programme to accommodate his risk items and also provide time for correcting mistakes
When there is a delay at the middle of the project, would you consider the actual delay or the delay for the whole period?
The actual delay caused by the item in question.
It is not fair to offset against any float time the contractor may have built up through good progress.
What is a programme?
A programme describes the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time.
What do programmes identify?
Can you name some types of Programming Techniques
- The Program Evaluation and Review Technique (PERT).
Who’s responsibility is it to monitor the contractors working schedule?
The PM’s so they can check?
What is the critical path?
What is PERT?
Programme, Evaluation, and Review Technique
You create three estimates for the duration of a project,
What can be identified from the project programme?
What should a programme help you do?
What types of Programme are there?
What goes into the Clients Overall Programme?
What goes into the design Programme?
• It describes the sequence of design tasks, i.e. from the process of design from inception through the Technical Design.
What goes into an information release schedule?
What goes into the Contractors Master Programme?
• The schedule and sequence of construction activities.
Can you employ a consultant to produce a programme?
Yes, on large projects they can prepare the outline programme.
What should you consider when preparing a programme?
• Items with a long lead-in. • Pre-contract works. • Pre-fabrication elements. • Works outside of the main contract. • Relationships with other projects. • Phasing and Sectional Completion. BD Department
What should a PM do when receiving a contractors programme?
• Check that it is not front loaded.
- Check the activity timescales are reasonable and realistic
What is a Gantt chart?
• A way of displaying a programme, through a combination of bars, each relating to an activity and having a specified duration.
What does a Gantt chart programme show?
The: o Start Date. o Duration. o Completion date. o Of both activities and the project as a whole.
What are the advantages of a Gantt chart?
What is Critical Path Analysis?
• A way of analysing the programme, to see if the critical path duration can be shortened or activities on it altered.
What do you aim to identify when undertaking a Critical Path Analysis?