DFWCS #1 will immediately…
A. Go to single element control
B. Raise its master controller output
C. Fully close its downcomer control valve
D. Reduce the speed of both MFPs
A. Go to single element control
If the Tc reported to the Control Room Supervisor (CRS) is below __F, the operator should __.
A. 560; ensure feed flow is not excessive.
B. 560; open Atmospheric Dump Valves (ADVs).
C. 564; ensure feed flow is not excessive.
D. 564; open Atmospheric Dump Valves (ADVs).
A. 560; ensure feed flow is not excessive.
If Tavg fails HIGH during a reactor trip, both DFWCS would…
A. Be prevented from entering RTO.
B. Prevent feeding of the Steam Generators
C. Feed at a minimum rate as permitted by RTO.
D. Feed at a maximum rate as permitted by RTO.
D. Feed at a maximum rate as permitted by RTO.
While performing NORMAL OPERATION with SBCS, how many (if any) SBCS valves may have a manual permissive inserted with the valve in AUTOMATIC?
A. 0
B. 1
C. 2
D. 8
B. 1
If Main Steam Header Pressure transmitter, SGN-PT-1027, fails LOW, __.
A. ALL SBCS valves would close IMMEDIATELY.
B. ALL SBCS valves would close quickly after 15 seconds.
C. SBCS valves with AUTO PERMISSIVE would close IMMEDIATELY.
D. SBCS valves with AUTO PERMISSIVE would close quickly after 15 seconds.
D. SBCS valves with AUTO PERMISSIVE would close quickly after 15 seconds.
Based on this, the Reactor Power Cutback System will drop the selected CEAs and the Main Turbine will (1) and (2).
A. (1) Setback (2) Continuously runback
B. (1) Setback (2) not runback below 60%
C. (1) Not Setback (2) Continuously runback
D. (1) Not Setback (2) Not Runback below 60%
B. (1) Setback (2) not runback below 60%
Which of the following conditions are required for the Steam Bypass Control System (SBCS) to generate an Automatic Withdrawal Prohibit (AWP) signal to CEDMCS?
A. Tavg > 573.5F
B. Quick Open Block Group X.
C. Quick Open Block Group Y.
D. Modulation demand and Permissive met.
D. Modulation demand and Permissive met.
A. Normal Plant Stabilization following a manual RPCB.
B. Normal Plant Stabilization following an automatic RPCB.
C. A RPCB followed by RISING RCS pressure and temperature due to secondary power (STEAM DEMAND) being LOWER than primary power.
D. A RPCB followed by LOWERING RCS pressure and temperature due to secondary power (STEAM DEMAND) being HIGHER than primary power.
D. A RPCB followed by LOWERING RCS pressure and temperature due to secondary power (STEAM DEMAND) being HIGHER than primary power.
The RPCB signal is only present for a short period of time following the RPCB, after this time, the dropped CEAs __ to the __.
A. Are able to respond, RRS and/or CEDMCS operator control module.
B. Are able to respond, RRS but not CEDMCS operator control module.
C. Are not able to respond, RRS and/or CEDMCS operator control module.
D. Are not able to respond, RRS but will respond to the CEDMCS operator control module.
A. Are able to respond, RRS and/or CEDMCS operator control module.
In order to accomplish this, the Secondary Operator must…
A. First reduce the LOAD LIMIT potentiometer until the LOAD LIMITING light comes on, then pick up load as necessary.
B. Reduce turbine load below 15% to clear the SETBACK, then raise load as desired using the LOAD LIMIT potentiometer.
C. Simply raise the setting of the LOAD LIMIT potentiometer, since the setting of this control follows the SETBACK and RUNBACK down.
D. Must perform this manipulation with the LOAD SET pushbutton since the LOAD LIMIT potentiometer is out of the circuit until the original (pre-rejection) load has been established.
A. First reduce the LOAD LIMIT potentiometer until the LOAD LIMITING light comes on, then pick up load as necessary.
Which of the following describes the RRS response?
A. No CEA motion will occur due to an AMI being generated.
B. CEAs should insert a few steps due to the Rate of Change circuit sensing a power error.
C. CEAs should withdraw a few steps due to the Rate of Change circuit sensing a power error.
D. No CEA motion will occur due to the Rate of Change circuit eliminating the effects of the instrument failure.
B. CEAs should insert a few steps due to the Rate of Change circuit sensing a power error.
Which ONE of the following describes the plant response?
A. Pressurizer pressure will lower.
B. Pressurizer pressure will increase.
C. SBCS will runback the Main Turbine.
D. SBCS will receive a quick open block.
A. Pressurizer pressure will lower.
Which ONE of the following describes RRS and PLCS response to this failure?
A. AMI is generated, PLCS auto setpoint rises.
B. AMI is generated, PLCS auto setpoint lowers.
C. AWP is generated, PLCS auto setpoint lowers.
D. AWP is generated, PLCS auto setpoint rises.
B. AMI is generated, PLCS auto setpoint lowers.
PZR pressure transmitter ‘100Y’ failing high will result in:
A. All pressurizer heaters energizing.
B. All pressurizer heaters de-energizing.
C. The SBCS valves receiving an auto permissive signal.
D. The SBCS valves receiving an auto modulation signal.
C. The SBCS valves receiving an auto permissive signal.
Which ONE of the following heater trips will function on the Train A PZR backup heater?
A. Low PZR level and electrical protection ONLY.
B. High PZR pressure and electrical protection ONLY.
C. Low PZR level, high PZR pressure, and electrical protection.
D. High PZR level, low PZR pressure, and electrical protection.
C. Low PZR level, high PZR pressure, and electrical protection.
Based on the above conditions and NO OPERATOR ACTION, Letdown flow will..
A. Lower to 0 gpm.
B. Remain unchanged.
C. Rise to 135 gpm and stabalize.
D. Lower to 30 gpm and stabilize.
A. Lower to 0 gpm.
NOTE- Believe C is also a correct answer
Which of the following describes an expected response of the PLCS/PPCS?
A. All backup heaters energize.
B. The standby charging pump starts.
C. The letdown control valves throttles closed.
D. The pressurizer pressure master controller, RCN-PIC-100, output lower.
A. All backup heaters energize.
Which ONE of the following states how the CPC calculated value of LPD would change if a dilution was started as rods were inserted into the core?
LPD would…
A. rise and LPD margin will lower.
B. lower and LPD margin will rise.
C. remain the same and margin will remain constant.
D. lower and margin will initially remain constant and then lower.
A. rise and LPD margin will lower.
Assume that the plant had been at steady state 100% power for several days and all COLSS inputs are operable and accurate. What is the effect on COLSS plant power if one T-cold instrument begins to to read 5F lower than actual?
A. The change WILL NOT be seen on the COLSS plant power meter on B04.
B. The COLSS plant power meter will immediately (within one minute) read higher than actual, and will remain there until the instrument is taken out of scan.
C. The COLSS plant power meter will immediately (Within one minute) read higher than actual, but within the following hour, plant power will return to its actual value.
D. The COLSS plant power meter will not immediately (within one minute) change, but within the following hour, plant power will rise to greater than its actual value and remain there until the instrument is taken out of scan.
C. The COLSS plant power meter will immediately (Within one minute) read higher than actual, but within the following hour, plant power will return to its actual value.
Based on these conditions, how will the system respond?
A. Train ‘A’ CPIAS and a Train ‘A’ and ‘B’ CREFAS actuate.
B. Train ‘A’ and ‘B’ CPIAS and a Train ‘A’ and ‘B’ CREFAS actuate.
C. Trip and BYPASS lights to go out as the channel is restored to service.
D. BYPASS light to remain lit. as the channel will not come out of bypass in these conditions.
B. Train ‘A’ and ‘B’ CPIAS and a Train ‘A’ and ‘B’ CREFAS actuate.
Which ONE of the following will cause the Reactor Regulating System to generate an Automatic Motion Inhibit (AMI)?
A. Tc=576F.
B. Tavg=587F with Tref=580.
C. Control Channel #1 at 99%, Control Channel #2 at 93%, RRS selected to Control Channel 2.
D. Control Channel #1 at 99%, Control Channel #2 at 93%, RRS selected to Average Control Channel.
D. Control Channel #1 at 99%, Control Channel #2 at 93%, RRS selected to Average Control Channel.
Which of the following instrument/signal failures could impact feedwater flow with the Feedwater Control System in automatic at 10% power?
A. Steam Flow.
B. Feedwater Flow.
C. Turbine Load Index
D. Log Safety Channels
C. Turbine Load Index
NOTE: Uses TLI and SBCS Demand for Anticipatory
What will prevent a quick open of ALL SBCS Vavles?
A. Reactor trip and low RCS Tave.
B. Reactor trip and high RCS Tave.
C. A loss of steam to a Main Feed Pump.
D. Any reactor trip, regardless of RCS Tave.
A. Reactor trip and low RCS Tave.
If CEDMCS is left in AUTO SEQUENTIAL, the Operating Crew should expect CEAs to…
A. Start stepping in.
B. Receive a withdraw signal (with no rod motion).
C. Remain in their present position due to an AMI.
D. Remain in their present position due to an AWP.
A. Start stepping in.