What are considerations for Project Cost Management
What Processes are a part of Project Cost Management?
What is the contingency reserve?
Time/money allocated in the schedule or cost baseline for known risks with active response strategies.
PM Role
When thinking about cost and impact, what is important to remember?
Projects spend money from initiation to completion, mistakes can have dramatic effects.
What is the cost baseline?
The approved version of the time-phased project budget, excluding any mgmt reserves.
Used as a basis for comparison to actual project results and can only be changed through formal change control procedures
What is a cost management plan?
What is estimate costs?
What is a cost estimate?
Describe progressive elaboration in terms of Cost Management, and ROM
What is Analog estimating in terms of cost management?
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
- Frequently used to estimate project costs when there is limited information
- Less-costly, not the most accurate
Uses ratios comparing the size of the previous work to the size of the current work, then multiplies the cost of the previous project by the ratio
What is Parametric Estimating?
What is bottom up estimating?
What is three point estimating?
What is Triangular distribution and when to use it?
Type of 3 point estimating.
• cE = (cO + cM + cP)/3
Use when there is insufficient historical data
What is Beta Distribution and when to use it?
Type of 3 point estimating.
• cE =(cO + 4cM + cP)/6
• Used when 1+ scenario’s is more likely to occur
Provides a weighted average
What is the key benefit of determining the budget?
determining the cost baseline against which project performance can be monitored and controlled
What is the difference between the project budget and the cost baseline?
Project Budget = all funds authorized to execute the project
Cost Baseline = approved version of the time-phased project budget that includes contingency reserves but excludes mgmt reserves
Projects can have multiple cost baselines
What is needed to efficiently control costs, blue sky?
What does it say about the project if funds are being consumed too slowly or quickly?
Slowly - might be a bad thing, work might not be progressing or being finished in certain areas
Fast - change request needs to be submitted to increase/reallocate the budget item
What do significant deviations from the cost baseline result in?
What is trend analysis?
What is Reserve Control?
Explain the “To-complete performance index”