What is the main purpose of the project schedule?
To provide a detailed plan for how and when the project will deliver the results defined in the project scope.
Communicating and managing
Role of the PM in Schedule Management
What is the schedule baseline, and how is it developed?
It is the formally accepted schedule that is created when the schedule developed at the beginning of the project.
Steps:
- Choose a scheduling method
- Entering Project info into a schedule tool to create a schedule model
Why is it important to keep the project schedule flexible?
What are the 6 project schedule processes?
Planning Process Group: - Develop Schedule - Plan Schedule Mgmt - Define Activities Process - Estimate Activity Durations - Sequence Activities Monitoring and Controlling: - Control Schedule
What are some consideration to tailor Project Schedule Management?
What is the define activities process?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables
What is a project schedule composed of?
- Scheduling method • EX: Critical path, agile - Project specific data • EX: activities, planned dates, durations, resources, dependencies, constraints - A schedule model
What is the schedule management Plan?
Who should be included in a project schedule development meeting?
Project manager Project Sponsor Selected Project Team Members Selected Stakeholders Anyone with responsibilities for schedule planning or execution
What is progressive elaboration?
An iterative process of increasing the level of detail in a PM Plan as greater amounts of information and more accurate estimates become available.
What is rolling wave planning?
Iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level.
It is a form of progressive elaboration applicable to work packages, planning packages, and release planning when using an agile or waterfall approach
What does define activities process do regarding work packages?
Reduces work packages into specific activities
What is decomposition?
in relation to schedule mgmt
A technique used for dividing the project scope and deliverables into smaller, more manageable parts
Defines the final outputs as activities rather than deliverables, as done in the WBS process
What are the 4 types of logical relationships in PDM?
What is the precedence diagramming method? (PDM)
What is Dependency Determination and integration?
Allow you to sequence your activities according to how they are dependent on each other. There are 4 Dependencies
What are the 4 types of dependencies?
What process turns into the schedule baseline going forward?
Sequence Activities
What do schedule network diagrams do?
Diagrams that identify and document relationships among project activities. They show you the logical sequence of project work.
What is the most commonly used precedence relationship when using PDM?
Finish to Start = FS
Start to Finish is rarely used (SF)
What are leads and lags?
Refinements applied during network analysis to develop a viable schedule by adjusting the start time of the successor activities.
Leads: used to advance a successor activity with respect to the predecessor activity
- Represented as a negative value
Lags: used where processes require a set period of time to elapse between the predecessors and successors without work or resource impact
- Represented as a positive value
What are the 4 factors to consider when estimating activity durations?
What may determine the duration of an activity?