The project charter
high level statement of what is to be done and the boundaries of a project
WBS
Work Breakdown Structure
PM tools
critical path
series of activities that have zero float
activity float
a measure of an activities flexibility
free float
float an individual activity can use up without effecting the early start of the next activity
total float
the float shared with other activities in a group (arm)
TF
Total Float = LF - ES - duration
SF
Start Float = LS - ES
FNF
Finish Float = LF - EF
Shortcomings of PDM
‘Parkinsons Law’
an activity will expand to fill the time available
‘student syndrome’
human nature for many means activities are left to the last possible minute