Which type of conflict resolution is usually the best when tensions and emotions are high?
Withdrawal
At what stage of Tuckman’s Ladder do team members complete the work and move on from the project?
Adjourning
What is the best practice in regard to the Team Charter?
The Team Charter works best when the team develops it, or at least has an opportunity to contribute to it.
Name three hierarchical charts used in Project Resource Management?
What are the various types of communication? (6)
How should stakeholders be classified?
According to their interest, influence, and involvement in the project.
What are the steps involved in the Identify Stakeholders process?
What are the various methods used to classify stakeholders?
What information about the project stakeholders does the Stakeholder Register typically contain?
What is the purpose of managing stakeholder engagement?
It allows the project manager to increase support and minimize resistance from stakeholders.
What are the 5 key components of a basic communication model?
Give at least three examples of noise in communication.
What are the 3 types of communication methods?
Give at least 3 examples of Push Communication.
Give at least 3 examples of Pull Communication.
In which document would you find a glossary of common project terminology?
The Communications Management Plan
In which document would you find the template for project status reports?
The Communications Management Plan
In which part of the project life cycle is Monitor Communications process performed?
Throughout the project life cycle
Give three examples of formal written communication.
Give two examples of formal verbal communication.
Give two examples of informal written communication.
Give two examples of informal verbal communication.
The verbal elements of a speech outside of spoken words, such as pitch, tone, rate, etc., are known as ______________ factors.
The verbal elements of a speech outside of spoken words, such as pitch, tone, rate, etc., are known as <u>paralingual</u> factors.
What information is usually distributed to stakeholders when the project is under execution?
Performance reports, deliverable status, schedule progress, cost incurred, presentations, and other information required by stakeholders.