Give 5 examples of Enterprise Environmental Factors.
Are the human resource policies of an organization considered an Enterprise Environmental Factor or an Organizational Process Asset for the project?
Organizational Process Asset
Is organizational structure of the performing organization considered an Enterprise Environmental Factor or an Organizational Process Asset for the project?
Enterprise Environmental Factor
Is resource availability considered an Enterprise Environmental Factor or an Organizational Process Asset for the project?
Enterprise Environmental Factor
Are project management plan templates considered an Enterprise Environmental Factor or an Organizational Process Asset for the project?
Organizational Process Asset
Give three examples of tangible elements of business value for business driven organizations.
Give three examples of intangible elements of business value for business driven organizations.
What are the various types of PMO structures within organizations?
How does Organizational Governance impact projects within the organization?
Organizational Governance may impose constraints on the project.
_________________ aligns projects, programs, or operations to the organizational strategy.
<u>Portfolio Management</u> aligns projects, programs, or operations to the organizational strategy.
Are project closure requirements considered an Enterprise Environmental Factor or an Organizational Process Asset for the project?
Organizational Process Asset
What are the two types of Enterprise Environmental Factors?
External and Internal
What are the two categories of Organizational Process Assets?
What are the three organizational system factors that can influence projects?
What is the primary function of a PMO?
To support project managers.
Give some examples of project stakeholders.
Whom does the project manager usually report to in a Balanced Matrix organization?
Functional Manager
What are the two categories of Organizational Process Assets?
What are the 3 primary forms of organizational structures?
What are the 3 types of Matrix organizations?
How much authority do project managers have in a Balanced Matrix organization?
Low to moderate
Who controls the project budget in a Balanced Matrix organization?
It’s a mixed responsibility between the Functional Manager and the Project Manager.
Whom does the project staff report to in a Strong Matrix organization?
Both - the Functional Manager and the Project Manager - but the Project Manager has more authority on the resources than the Functional Manager.
In which organizational structure(s), the project has full-time administrative staff?