Describe Design-Bid-Build delivery method.
Owner contracts with A/E to produce construction docs, Owner then contracts with contractor to build. No contractual agreement between A/E and contractor, 3 options
Describe Construction Manager at Risk (CMAR) delivery method.
Owner contracts with A/E to produce construction docs, Owner contracts with Construction manager coordinate with A/E and construction, CM contracts with subcontractors to complete trades
Typical when Owner does not have building knowledge/experience
Describe Construction Manager as Agent/Advisor (CMa) delivery method.
Construction manager acts as owner’s agent, advise on project activities, can make decisions on behalf of owner
Describe Integrated Project Delivery (IPD) delivery method.
Two groups of individuals/companies that work together to deliver work, shared financial risk/reward, early involvement
One group decides, designs and determines, the other supplies, constructs and installs
Describe Design-Build delivery method.
Owner contracts with single entity to provide design and construction services
Describe Owner-Build delivery method.
Owner is involved in construction contracting for each portion of work, retains independent A/E for design and potentially CA
What are Design-Bid-Build variations in construction documents?
What are Construction Manager at Risk (CMAR) variations in construction documents?
What are Construction Manager as Agent/Advisor (CMa) variations in construction documents?
What are Integrated Project Delivery (IPD) variations in construction documents?
What are Design-Build variations in construction documents?
What are Owner-Build variations in construction documents?
What are the primary goals of evaluating systems, assemblies and materials?
Meet project requirements (owner’s requirements) and design intent
Besides design intent, what are systems, assemblies and materials evaluated against?
Identify the primary project components against which proposed systems, assemblies and materials are evaluated.
What is the typical series of activities for evaluation of systems, assemblies and materials?
What PRODUCT attributes should be evaluated for product performance?
What steps are taken to confirm products meet project requirements?
What are the tasks to coordinate product information between the drawings and specs.
How should product information be coordinated between the drawings and specs?
What common codes govern construction projects?
Regulator requirements - codes and standards
What information is important for analyzing products for compliance with applicable codes?
Which aspects of the product are covered in code compliance evaluation
Which standard is referenced in the specifications.
What common components are evaluated when assessing interior conditions?
Why is it important to evaluate material durability with interior conditions?