1
Q

Name some types of procurement routes

A

Single stage - Price offered for the whole of the construction works
Two - stage - Hand in hand with PCSA, price for PCSA to aid in design and pre construction activites, then revisited for a price to complete construction works
Negotiated tender - Single stage with a single contractor. Contractor returns price then the price is negotiated after

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Advantages and disadvantages of single stage

A

ADV: Cost certainty early, most competitive price
Dis: Contractor could not fully understand requirements meaning risk allowance to be higher, Longer programme to include tender period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Advantages and disadvantages of two stage

A

Adv: increased contractor involvement in design, some degree of competition, ability to overlap design and tendering

dis: programme implication for tender process, lack of full competition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Name some types of tender selection

A

Open tendering (anyone can express interest via find a tender)
Selective tendering (shortlisted contractors)
single contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a PQQ and why would you use it

A

Pre qualification questionnaire

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What would you include in a PQQ

A

Case studies of relevant projects
Expertise to similar projects
company accounts information
H&S information
Methodology statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What information would you include in a traditional contract type

A

Bill of quants or pricing doc
Preliminaries doc
design information
any CPD elements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What information would you include in a design and build contract type

A

Employers requirements
pricing doc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What information would you include in an NEC contract type

A

depends on options but:
Works infomation
Site information
Contract data part 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Alternative 2 in JCT

A

A method for dealing with tender qualifications or amendments. It provides a way for the employer to respond to a non complaint bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Name a time you have advised a client on procurement route

A

During an NHS hospital project, I advised that the optimal procurement route was traditional due to the relatively straightforward nature of the project, and the completion of a number of similar projects with experienced design teams and therefore the project could see cost efficiencies through lower prelims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What has MEAT been superseded by

A

MAT (Most advantageous tender) allows price to be optional giving authorities flexibility to focus on quality and social aspects of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

in your opinion which JCT contract has the most risk for the client and why

A

A traditional JCT form (i.e SBC) Due to client holding design responsibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Under the current market conditions, what is the preferred procurement route

A

Depends on the project completely. But I would recommend D&B due to transferring risk to the contractor and having a single point of responsibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What would you typically include in a tender pack

A

ITT, form of tender, draft contract, project information, tender scoring matrix, pricing doc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is alternate 1

A

A way of dealing with errors in tender submissions under the JCT

Alt 1 - Confirm or withdraw

17
Q

Under the alternate provisions in JCT what needs to be included?

A

Signed letter by both parties. Contractor to make an endorsement of their offer

18
Q

When should the selected alternate provision be stated and where?

A

Before the contractors are issued tender documents. The chosen provision should be indicated in the ITT and project information docs

19
Q

Why did you chose alternate 2?

A

Allowed for better partnering between the parties
Allowed for better tender competition and therefore better costs for the client