what is critical path analysis?
a network diagram that helps organise a businesses tasks in level of importance and allocates time needed to achieve each task
what is total float?
how long can one task go over without impacting the finishing time of the next task.
how do u calculate total float?
earliest finishing time of task A - duration - Earliest finishing time of task B
what is free float?
how much one task can go over without impacting the end time of the entire project. q
how do you calculate free float?
earliest start time - duration - latest finish time of task before