Strip Foundation Take Off
Drainage Take Off
NRM1 Cost Plan Structure:
0; Facilitating Works
1-8; Building works (see separate breakdown)
9; Preliminaries
10; Overhead & Profit
- Works Cost Estimate (Construction)
11; Design Team Fees:
Architect, Civils, M&E, Project Manager, Quantity Surveyor, Principal Designer
12; Other development:
Finance, Planning, Insurances, Party wall, Marketing, Ecology, Archaeology etc.
- Base Cost Estimate (Development)
13; Risk Allowances:
Design Development, Construction Risk, Employer Change, Employer Other
- Cost Limit exc. Inflation (Dev & Con x Inflation)
VAT assessment (requirement to be assessed by a tax specialist)
Dayworks
Principles of Measurement International (POMI)
BIM
Cost Approaches (detail)
GIA - £/m2
Strategic
Functional -£/per bed/person etc; Resi, Flats, Houses - Hospital; Beds – School; Nr of students
Feasibility
Elemental – NRM; Substructure, Superstructure etc
OoCE
Element – Ground Floor Slab, Upper Floor, Roof, External wall
Formal Cost Plan
Piled Foundation Take Off
What would you do if you weren’t sure on how to measure something?
I would review NRM1 if I was undertaking costing for a Cost Plan or NRM2 if more detail was required
GFS Take Off
Kings Tower - NIA to GIA
BoQ vs CSA Princess Street
NRM 2 - Foundation excavation
Difference between NRM 1 vs 2
NRM 1 - Cost planning (pre-contract)
NRM 2 - Detailed measurement (post-contract i.e. trade package award - greater detail required)
Importance of Measurement Rules
CESMM4 vs NRM 2
I understand that costing construction work varies dependent on which Royal Institute of British Architects (RIBA) stage the project is at. For example, costing approach would differ from the feasibility stage compared to RIBA stage 4.
Different buildings can be used in very different ways and as such I appreciate the importance of following the guidelines within the Code of Measurement Practice.
Meole Brace - When completing a RIBA stage 2 (should be 1) Order of Cost Estimate I quantified elements such as the ground floor slab by making design assumptions and utilising composite rates.
Which RIBA stage would you do an OoCE?
UPS
Early on in the project a redundant drainage run was identified which needed to be removed. I engaged with the Main Contractor in order to establish how best to agree a costs for the works.
What were the key components of work? Type of pipe, depth?
Wrexham
On the project there was a Provisional Sum included for the substation base. When the substation base design information became available, I reviewed the validity of the Main Contractors price from both a quantity and a cost perspective to ensure the change was in line with the contract.
What is a substation?
Oxford, Residential Apartments
I produced the pricing document for the scheme which was done by using RICS New Rules of Measurement 2 (should be 1). Producing the pricing document (Contract Sum Analysis) aided in ensuring all components of work were covered and so tender returns could be readily compared to one another.