When can a SRO perform control board manipulations?
When directed by SM during POP04s, POP05s, POP09s, or SAMGs
Taking Action to save a life
Designated as RO in logbook

When performing a controlled shutdown for a LCO action statement, how long does it take to shutdown the plant?
Should start shutting down as soon as you know you will not be able to fix the problem.
Note:
Adjusted to coincide with Tech Spec action times.
When conditions make an alarm expected?
Caused By:
Current Operations
Surveillances
Testing
Known Issues
Maintenance
Direct Operator Actions
When multiple alarms are received (≥ 3) due to a plant transient, normal alarm response is suspended. When is it reinstated?
US / SM using a crew update
When should peer checks be used?
Risk important actions of medium risk procedures
Supervision cannot perform peer checks.
Note:
Peer checks not required for POP04s and POP05s.
When must you notify the FAA that the aviation lights are not working?
Lights not working for > 30 mins
Operability calls based on chemistry samples should be made after a backup sample is taken. When does the LCO clock begin if deemed inoperable?
Starts when initial sample was taken
What is the minimum shift complement?
SM (2)
US (2)
STA (1)
RO (4)
ENS Communicator (1)
Safe S/D Plant Operators (4)
State / County Communicator (1)
When should outdoor cranes be secured?
Wind Speeds > 30 mph
Who must be notified if a licensed operator fails a random breathalyzer test?
Unit Operations Manager
When is climbing authorized to reach a component?
Designed access system is not feasible / practical
Need approval of the supervisor
According to 10CFR50.72, Immediate Notification Requirements for Operating Nuclear Power Reactors, what situations require the NRC to be notified within 1 hour?
Emergency Class Declared
Deviation from Tech Specs
Safety Limit / T.S. Section 2.0 Exceeded
Unplanned Criticality
Radiological, Security, Environmental Events
When performing a critical step, what is required by the conduct of operations?
Supervisory Oversight
Peer Check OR Dual Verification
When a safety-related MOV is manually manipulated, what is required by the conduct of operations?
Shall be evaluated for OPERABILITY by US/SM
How long can minimum crew staffing be violated?
2 hrs

How many plant operators are required for shift manning to satisfy tech specs?

When must a RP technician be on site?
When fuel is in the reactor