What are your actions for primary chemistry action level 3?
Generate a CR
S/D immediately
Lower temperature to < 250 ˚F as rapidly as possible.
How long does the STA have to get to the control room once notified?
10 mins
What is the objective of secondary chemistry action level 3?
To correct a condition that can result in rapid corrosion of a secondary side component during continued operation.
Plant shutdown will minimize impurity ingress and limit exposure of steam generator, turbine, and other secondary materials to corrosive solutions.
What do the different primary chemistry action levels mean?
When can the STA stand watch as the Unit Supervisor, Primary RO, or Secondary RO?
US / RO must be available to re-relieve the STA if STA becomes activated
US / RO must be in same unit as STA
US / RO must perform shift turnover on same unit
What is STP required to notify the owner QSE’s of?
Power reductions > 25 MWe (Non-Peak)
Power reductions > 5 MWe (Peak)
Unit / Plant Shutdowns
Changes in scheduled power generation
Notifications made by EMS website and then followed by a telephone call.
Can alternate performance be applied to POP04’s and POP05’s?
No
Only applies to operating procedures
What are your actions for primary chemistry action level 1?
Generate CR
Bring back in spec within 7 days
If cannot be fixed within 7 days, then more formal corrective actions will be performed.
What chemistry transients warrant a Rx trip?
CP Fully bypassed
AND
Condensate Pump Discharge cation conductivity verified > 1.0 µS/cm
SG Cation conductivity rising
AND
SG Na, Cl, or SO4 > 1000 ppb
SG Cation conductivity > 15 µS/cm
AND
SG Na rising
When is the STA activated?
Emergency Plan Entry
EOPs entered
SM / STA discretion
What actions shall be performed for a secondary chemistry action level 2?
Generate CR
Take actions for safe and orderly reduction of power to ≤ 50% and achieve ≤ 50% power within 24 hours of entering Action Level 2.
Have 300 hours until action becomes action level 3
Power reduction may be terminated when no longer in action level 2 but may not raise power until out of action level 1.
What are your actions for primary chemistry action level 2?
Generate CR
Fix within 24 hrs
If cannot be fixed within 24 hrs, S/D plant to cold S/D.
If heating up plant and > 250 ˚F and Cl, SO4, Fl > 150 ppb for 24 hrs or O2 > 100 ppb for 24 hrs then lower temperature < 250 ˚F.
What is the objective of secondary chemistry action level 1?
Identify and correct the cause of an out-of-normal value without a power reduction
What actions shall be performed for a secondary chemistry action level 1?
Generate CR
Return parameter < Action Level 1 Value
Have 21 days until it becomes action Level 2
What is the objective of secondary chemistry action level 2?
To minimize corrosion by operating at reduced power while corrective actions are taken.
If a chemistry waiver is desired and the waiver is for a control parameter, whose concurrence must be obtained?
Plant Manager
Chemistry Manager is required for all waivers.
What actions shall be performed for a secondary chemistry action level 3?
Generate a CR