What does the risk assessment calculator assess?
Incremental Conditional Core Damage Probability
Weekly Trip Risk Probability
Used in MODES 1 and 2
What surveillances does the plant surveillance program procedure govern?
Tech Specs
TRM
ODCM
What does front stop completion time and the back stop completion time mean?
Note:
Risk-Management Technical Specifications (RMTS): Plant-specific set of configuration-based Technical Specifications, based on a formally approved configuration risk management program and associated probabilistic risk assessment, designed to supplement previous conventional plant Technical Specifications.
What does it mean when a piece of equipment is classified as (a)(1) or (a)(2)?
Requires increased attention to improve performance
Performing adequately
Who approves risk management actions?
Plant General Manager
Shift Manager in charge of implementing actions.
What must be done if a SR is interrupted and that interruption extends past shift change?
Suspend the SR
Who must the test coordinator inform once the SR is completed, suspended, or has failed?
Shift Manager
Test coordinator will forward results to the surveillance scheduler.