What does the Project Programming /Scheduling consist of?
What is the goal of Network Analysis?
Mention some Network Analysis methods.
Explain CPM in detail.
What are the different types of Precedence Relations?
What is the procedure for CPM?
How do you calculate Total Float (TF)?
TF = LF - ES - D
TF = LS - ES
TF = LF - EF
What does TF=0 mean?
It means that there is no programming flexibility
Give examples of Activity Resources.
What can be done to combat resource constraints?
Software can address global resource constraints.
Planner can use artificial precedence to ensure resources are not needed simultaneously.
What are the consequences of Sub-optimality?
Due to a lack of consideration for resource demand over time, the project can have sub-optimal results. The consequences are:
What is Resource Levelling?