What is “Global estimate” also called and what does it rely on?
Also known as:
Relies on a library of archive costs for similar projects related to its overall capacity or size.
Cost=historical cost / capacity rate * new project capacity
Give some examples of historical data that can be used in global estimation.
What are some problems with global estimating?
Does the cost of the project include:
How the measurement of the capacity is defined.
Not comparing with similar projects:
What is “Factorial Estimating”?
Some projects have a central fixed plant element, the cost of which can be determined accurately and in advance from suppliers. The cost of ancillary and peripheral engineering are calculated using a factor of the main plant element. (Also known as “Lang Factors”).
The reliability and accuracy of the factors heavily influence the overall reliability of the estimate.
The accuracy of the estimate also depends on the reliability of the price of the plant item.
What is “Labour-hours estimating”?
The simplest and earliest estimating techniques. Requiers some knowledge of how an operation is to take place (similar operational estimating).
Suitable for labour intesive operations such as fabrications and mechanical/electrical installations.
The number of hours a project will take is determined and then multiplied by and appropriate labour all-in rate.
The whole project cost is determined by adding on allowances for materials and plant.
What is the most common reason for undertaking an estimating exercise?
To prepare a tender, which is needed to be as accurate as possible for the construction company.
If the estimate is too high, the chance of winning the work is reduced.
if the estimate is too low the change of making a profit is reduced.
When doing a tender estimate, it is generally not suitable to use “Global estimate”, “Factorial Estimate” or “Labour-hour estimate”. What estimates are used instead?
Unit-rate and Operational estimates since they can be very detailed. However, they require a lot of cost data.
What is “Unit-rate Estimating”?
What is output rate?
Also known as wastage. For example:
Material - rebar 1.1 tonnes/tonne
Labour - Steelfixer 0.054 tonnes/hr
Plant - Crane 5 tonnes/hr
How do you calculate Direct costs?
Wastage: Rebar = 1.1 tonnes/tonne
Quatation for steel: Rebar = £397.93 per tonne
Direct costs = Wastage * Cost per unit = 1.1 * 397.93
What are some problems with unit-rate estimating?
What is “Operational estimating”?
It is the most fundamental type of estimating and is compiled from a consideration of the constituent operations and activities that are indicated in the construction programme.
It therefore needs documents which indicate the way work will be undertaken. This gives the estimator information which can be use to give a very detailed estimate.
This estimate allows for:
- Idle time.
- Uncertainties and risks. (Shows basic sources of costs, sensitivity of estimate to changes in assumptions and methods can be investigated, the reasons for variations in costs can be investigated).
- However, the process is time consuming, but does provide a library of operational data.
How is the cost of the project different from the tender bid?
The tender bid is different since the contractor must allow for risk, profit and overheads. These extra costs are termed “uplift”.
What is the estimators’ report used for, and what does it consist of?
The estimators’ report serves to provide the senior management with all the information they need to assess the commercial aspects of the project. It consists of: