What is a “Tender Enquiry Document”?
Used to inform tenderers of what is required at invitation to Tender stage.
What is Tender Documents?
Form the tenderer’s offer.
What is “Contract Documents”?
How are the contractors selected for invitation to tendering?
The contractors can be selected using something called “Two Stage”, what is this?
- Contractors who contribute to design may go forward to next stages.
The contractors can be selected using something called “Negotiated”, what is this?
What are some key points to look for when evaluating a tender?
Name the broad stages in contract management.
What is a “Letter of Acceptance”?
A letter of acceptance is used to inform the successful tenderer, after they have been evaluated.
This is an unconditional acceptance and constitutes a legally binding contract.
If an original offer has been amended in any way through negotiations, the amendments must be documented and referred to once an offer is accepted.
What should a Letter of Acceptance contain?
Why would a Letter of Intent be used instead of a Letter of Acceptance, and what does this do?
A LoA effectively forms a contract. If the Principal isn’t in a position to actually form a contract at this stage a Letter of Intent can be used instead.
A LoI advises the tenderer so that they may initiate construction mobilisation and should:
- Advise that full acceptance will be by a certain date.
- If contract not formed, expenses will not be paid unless specifically stated.
BEWARE, LoI is not legally binding!
Except the LoA or LoI, what else should be done to notify the tenderers?
What is “Instrument of Agreement”?
Also called “The agreement” and”Form of Agreement” and is a simple document
What are the Conditions of Contract document?
The conditions of contract document relates to the contract between the Principal and the Contractor to construct the works. In essence, it identifies the parties involved in the contract and defines their roles and responsibilities.
It will also lay down how to Contractor is to be paid and will allocate responsibility for some of the construction risks that are known to occur frequently.
It contains all the clauses relating to the respective rights and obligations of the parties of the contract. Mostly administrative provisions as distinct from technical requirements. Technical matters related to the nature of the project should be strictly kept to the drawings and specifications.
Many engineering contracts are related to projects of a similar nature. They should therefore be conducted using Standard Conditions of Contracts. Give some examples of these.
FIDIC, Federation Internationale des Ingenieurs-Conseils (Power plant installation project)
IChemE. (“Red book” - Lump sum, “Green Book” - Reimbursable and “Burgundy Book” - Target Cost).
MF/1 (ImechE/IET)
However, all projects are in some way unique and will therefore require particular requirements. Therefore there are two parts to any set of conditions:
Part 1: General conditions (With Annexure).
Part 2: Supplementary Conditions.
What are the three main pillars of “New engineering contracts” published 1993?
Name some variants to “New Engineering Contracts”.
Name some different options for contracts.
What are the main clauses?
What are “Compensation Events”?
Events that occur during the course of the works that cause the completion to be delayed usually result in additional payment being made to the contractor and may result the change to the completion date. However, it must not be the contractor’s fault.