1
Q

Bespoke oak reception desk – detailed build-up and rate considerations?

A

Construction build-up:

  • Set out joinery (item)
  • Fabricate carcass in MDF/ply (m²)
  • Apply oak veneer / solid oak sections (m²)
  • Form worktop (m²)
  • Install fixings and supports (item)
  • Integrate services (power/data/lighting) (item)
  • Deliver and install on site (item)

Rate build-up:

  • High material cost (oak)
  • Skilled joinery labour (workshop + install)
  • Bespoke fabrication premium

👉 Key driver: craftsmanship + bespoke design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Yorkstone paving – detailed build-up and rate considerations?

A

Construction build-up:

  • Excavate to formation (m³)
  • Lay and compact sub-base (m³)
  • Apply mortar bedding layer (m²)
  • Lay Yorkstone slabs and align (m²)
  • Point joints (m²)
  • Install edge restraints (m)

Rate build-up:

  • High stone material cost
  • Skilled labour for laying
  • Cutting waste allowance

👉 Key driver: stone cost + labour precision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Gravel – detailed build-up and rate considerations?

A

Construction build-up:

  • Excavate area (m³)
  • Install geotextile membrane (m²)
  • Place and compact sub-base (m³)
  • Lay bedding layer (m²)
  • Spread gravel finish (m²)
  • Install edging (m)

Rate build-up:

  • Low material cost
  • Plant for compaction
  • Sub-base dominates cost

👉 Key driver: groundwork not finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Piled foundations – detailed build-up and rate considerations?

A

Construction build-up:

  • Set out pile positions (item)
  • Drill/bore piles (m)
  • Install casing if required (m)
  • Insert reinforcement cage (tonne)
  • Pour concrete (m³)
  • Cut pile heads (item)
  • Construct pile caps (m³)
  • Cast ground beams (m³)

Rate build-up:

  • Specialist piling contractor
  • Piling rig (major plant cost)
  • Concrete + reinforcement
  • Spoil disposal (m³)

👉 Key driver: plant + depth + ground conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Raft foundation – detailed build-up and rate considerations?

A

Construction build-up:

  • Bulk excavation (m³)
  • Hardcore sub-base compacted (m³)
  • Sand blinding (m²)
  • Install DPM/gas membrane (m²)
  • Lay insulation (m²)
  • Edge formwork (m)
  • Fix reinforcement mesh (tonne)
  • Pour concrete slab (m³)
  • Finish slab (power float) (m²)

Rate build-up:

  • Concrete volume
  • Reinforcement density
  • Labour + concrete pump

👉 Key driver: slab thickness + steel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Strip foundation – detailed build-up and rate considerations?

A

Construction build-up:

  • Excavate trenches (m³)
  • Temporary support if required (item)
  • Pour concrete strip (m³)
  • Construct foundation blockwork (m²)
  • Backfill and compact (m³)
  • Install DPC (m)

Rate build-up:

  • Excavation depth
  • Concrete quantity
  • Bricklaying labour

👉 Key driver: ground depth + stability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Pad foundation – detailed build-up and rate considerations?

A

Construction build-up:

  • Excavate pad locations (m³)
  • Blinding layer (m²)
  • Install formwork (m²)
  • Place reinforcement cage (tonne)
  • Pour concrete pad (m³)
  • Install holding down bolts (item)
  • Backfill (m³)

Rate build-up:

  • Concrete + reinforcement
  • Formwork labour
  • Excavation

👉 Key driver: load + pad size

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Douglas Fir (glulam) frame – detailed build-up and rate considerations?

A

Construction build-up:

  • Prefabricate glulam members (m³)
  • Deliver to site (item)
  • Lift into place via crane (item)
  • Fix steel connections/plates (tonne)
  • Bolt and secure frame (item)

Rate build-up:

  • Engineered timber cost
  • Crane hire
  • Specialist install

👉 Key driver: crane + prefabrication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Oak frame – detailed build-up and rate considerations?

A

Construction build-up:

  • Prefabricate oak frame (m³)
  • Traditional joinery (mortise/tenon) (item)
  • Transport to site (item)
  • Crane installation (item)
  • Fix connections (item/tonne)

Rate build-up:

  • High material cost
  • Skilled labour
  • Crane

👉 Key driver: premium timber

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Concrete frame – detailed build-up and rate considerations?

A

Construction build-up:

  • Erect formwork (m²)
  • Fix reinforcement (tonne)
  • Pour concrete columns/beams/slabs (m³)
  • Cure and strike formwork (m²)

Rate build-up:

  • Reinforcement
  • Formwork labour
  • Concrete volume

👉 Key driver: labour + formwork

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Steel frame – detailed build-up and rate considerations?

A

Construction build-up:

  • Fabricate steel off-site (tonne)
  • Deliver to site (item)
  • Crane erection (item)
  • Bolt/weld connections (tonne)
  • Install metal decking (m²)
  • Apply fire protection (m²)

Rate build-up:

  • Steel tonnage
  • Fabrication
  • Crane

👉 Key driver: steel weight

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

LVT – detailed build-up and rate considerations?

A

Construction build-up:

  • Prepare subfloor (m²)
  • Apply smoothing compound (m²)
  • Apply adhesive (m²)
  • Lay LVT tiles/planks (m²)

Rate build-up:

  • Material cost
  • Fast installation
  • Minimal plant

👉 Key driver: finish quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Resin floor – detailed build-up and rate considerations?

A

Construction build-up:

  • Prepare substrate (grind/clean) (m²)
  • Apply primer (m²)
  • Apply resin base layer (m²)
  • Optional aggregate broadcast (m²)
  • Seal topcoat (m²)

Rate build-up:

  • Specialist labour
  • Material system cost

👉 Key driver: specialist install

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Parquet floor – detailed build-up and rate considerations?

A

Construction build-up:

  • Prepare subfloor (m²)
  • Apply adhesive (m²)
  • Lay timber blocks (m²)
  • Sand surface (m²)
  • Apply seal/lacquer (m²)

Rate build-up:

  • Labour intensive
  • Timber cost

👉 Key driver: install time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Carpet – detailed build-up and rate considerations?

A

Construction build-up:

  • Prepare subfloor (m²)
  • Lay underlay (m²)
  • Install gripper rods (m)
  • Lay carpet (m²)

Rate build-up:

  • Material spec
  • Quick install

👉 Key driver: carpet quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

LED handrail – detailed build-up and rate considerations?

A

Construction build-up:

  • Install handrail (m)
  • Integrate LED strip (m)
  • Conceal wiring (item)
  • Connect to power (item)

Rate build-up:

  • Joinery + electrical labour
  • Integrated system

👉 Key driver: coordination

17
Q

Lead roof – detailed build-up and rate considerations?

A

Construction build-up:

  • Install timber deck (m²)
  • Apply underlay (m²)
  • Fix lead sheets (m²)
  • Form joints and flashings (m)

Rate build-up:

  • High lead cost
  • Specialist labour
  • Waste allowance

👉 Key driver: material cost

18
Q

Green roof – detailed build-up and rate considerations?

A

Construction build-up:

  • Structural deck (m²)
  • Waterproof membrane (m²)
  • Root barrier (m²)
  • Drainage layer (m²)
  • Filter layer (m²)
  • Growing medium (m³)
  • Vegetation (m²)

Rate build-up:

  • Multiple layers
  • Specialist install

👉 Key driver: complexity

19
Q

Single ply roof – detailed build-up and rate considerations?

A

Construction build-up:

  • Structural deck (m²)
  • Vapour control layer (m²)
  • Insulation (m²)
  • Fix single ply membrane (m²)
  • Seal joints (m)

Rate build-up:

  • Membrane system
  • Insulation thickness

👉 Key driver: insulation + fixing method