What is the key difference between Employer’s Requirements and Contractor’s Proposals in JCT D&B?
Employer’s Requirements set out the Client’s design intent, performance requirements and specifications. Contractor’s Proposals explain how the contractor will meet those requirements and form part of the contract documents once agreed.
Who holds design responsibility under JCT Design and Build 2016?
The contractor holds responsibility for completing and developing the design in accordance with the Employer’s Requirements, including design carried out by novated consultants.
What is the role of the Employer’s Agent under JCT D&B?
The Employer’s Agent administers the contract on behalf of the Employer, including issuing instructions, assessing extensions of time and certifying payments, while acting fairly and in accordance with the contract.
Is Practical Completion defined in JCT 2016?
No, Practical Completion is not defined in JCT. It is generally understood to mean the works are complete except for minor defects which do not prevent beneficial occupation.
What is a Relevant Event?
A Relevant Event is a contractual event that entitles the contractor to an extension of time.
What is a Relevant Matter?
A Relevant Matter is an event that entitles the contractor to loss and expense in addition to any extension of time.
What is two-stage Design and Build?
Two-stage Design and Build involves appointing a contractor under a PCSA during Stage 1 to provide pre-construction services, with the contract sum agreed at Stage 2 before entering into the main building contract.
What is a PCSA?
A Pre-Construction Services Agreement is an agreement under which the contractor provides design input, programming, logistics and cost advice prior to execution of the main contract.
What happens if the Stage 2 price cannot be agreed?
The Employer may choose not to proceed with that contractor and can tender the works to others or renegotiate terms.
What is sectional completion?
Sectional completion allows different parts of the works to achieve Practical Completion on different dates, as defined in the Contract Particulars.
Where must sectional completion dates be stated?
They must be clearly defined in the Contract Particulars of the contract.
How are LADs applied under sectional completion?
Liquidated damages are apportioned to each section and apply only if that specific section is delayed beyond its completion date.
What is the difference between sectional completion and partial possession?
Sectional completion is planned and defined at contract execution. Partial possession occurs when the Employer takes possession of part of the works before Practical Completion and may affect LADs and insurance.
What legislation governs construction payments in the UK?
The Housing Grants, Construction and Regeneration Act 1996 (as amended).
What is the due date for payment?
The due date is the date from which the payment period begins, as stated in the contract.
What is the final date for payment?
The final date for payment is the last date by which the notified sum must be paid.
What is a Payment Notice?
A Payment Notice sets out the sum the payer considers due and the basis on which it is calculated.
What is a Pay Less Notice?
A Pay Less Notice allows the payer to pay less than the notified sum, provided it is issued within the contractual timeframes and sets out the calculation basis.
What is the notified sum?
The notified sum is the amount stated in a valid Payment Notice or, if none is issued, the contractor’s application.
What happens if a valid Pay Less Notice is not issued?
The payer must pay the notified sum, even if it is considered incorrect.
Why should you not certify work that has not been carried out?
Certifying uncompleted work could result in overpayment, increased insolvency risk and potential professional negligence exposure.
How would you defend your valuation in adjudication?
By relying on contemporaneous records, site inspections, photographs, marked-up drawings, contractual provisions and a clear audit trail.
What is retention?
Retention is a percentage withheld from interim payments as security against defective or incomplete works, typically released at Practical Completion and at the end of the defects period.
What is novation in Design and Build?
Novation is the transfer of the design consultant’s appointment from the Employer to the Contractor, so the contractor assumes responsibility for the consultant’s future design work.