What are the RIBA Stages of Work?
The RIBA Plan of Work consists of:
0 – Strategic Definition
1 – Preparation and Brief
2 – Concept Design
3 – Spatial Coordination
4 – Technical Design
5 – Manufacturing and Construction
6 – Handover
7 – Use
Cost certainty increases as the project progresses through the stages, with the majority of design risk reducing by Stage 4.
What are some sub-elements within superstructure?
Typical superstructure elements include: Frame (steel, concrete, timber)
Upper floors
Roof structure and coverings
External walls Windows and external doors
Internal walls and partitions
Stairs and balustrades
How would you price or measure superstructure elements?
This depends on procurement stage:
Frame: measured in tonnes (steel), m³ (concrete), or m²/m³ (timber frame)
Upper floors: m² including slab thickness External walls: m² including insulation, finishes, and substructure interface
Roof: m² including coverings and structure Internal partitions: m² or linear metres
I would refer to NRM2 for detailed measurement rules and include labour, plant, preliminaries impact, and waste allowances.
What are the different types of pile construction methods?
Common types include: Bored piles (CFA – Continuous Flight Auger)
Driven piles (precast concrete or steel)
Rotary bored piles Mini piles (restricted access sites)
CFA piles are common for low vibration environments such as schools.
Can you explain the build-up of pad foundations?
A typical pad foundation build-up includes:
Excavation to formation level Blinding layer (lean concrete)
Reinforcement cage
Concrete pour
Starter bars for columns
Backfill and compaction
Load is transferred from the column into the pad and then dispersed into the ground.
How did you quantify the bearing capacity?
I did not calculate bearing capacity myself. I reviewed the site investigation report which confirmed allowable bearing pressures and ground conditions.
I used the structural engineer’s proposed foundation sizing based on that data to inform cost comparisons.
How did excavation impact foundation choice?
Piled foundations required deeper excavation and disposal of spoil, specialist plant and potential muck-away costs.
Pad foundations required shallower excavation, reduced muck-away, and simpler ground preparation.
If ground conditions had been poor or bearing capacity insufficient, piles would have been required despite higher cost.
What were the programme implications of each foundation type?
Piled foundations: Specialist subcontractor Longer mobilisation period Lead-in time for piling contractor Sequential installation Pad foundations: Simpler construction Can be constructed by groundworks contractor Reduced lead times Faster progression to superstructure.
Why did pad foundations provide a cost saving?
Savings arose from: No specialist piling contractor Reduced plant requirements
Reduced excavation depth Lower concrete volume compared to deep piles
Reduced preliminaries due to shorter programme.
What was the cost of pile foundations?
For example: The piled foundation solution was approximately £450K-600K compared to £150K-300K for pad foundations, representing a saving of approximately X%.
How did you quantify concrete and reinforcement?
Concrete: Measured in m³ based on structural drawings and foundation sizes.
Reinforcement: Estimated using reinforcement ratios provided by the engineer or industry benchmarks (kg/m³).
Other items included: Excavation and disposal Blinding Formwork Plant Labour Ground preparation Testing Preliminaries impact.
Can you talk me through the Douglas Fir vs Oak cost exercise?
I reviewed:
Material supply rates
Fabrication costs
Installation methodology
Lead times
Structural implications
Handling requirements
Oak: Higher material cost
Specialist fabrication Off-site manufacture
Longer procurement lead time
Heavier structural members
Douglas Fir:
Lower material cost
Standard timber construction methods
Shorter lead time
Reduced reliance on specialist subcontractors
I presented a side-by-side cost and programme comparison.
How did you review procurement risks?
I considered:
Lead times
Supplier availability
Specialist labour dependency
Transport requirements
Installation complexity
Programme float
Oak carried higher procurement and supply chain risk due to specialist fabrication.
If the Client chose oak, what logistics plan would be required?
Early supplier appointment
Detailed fabrication drawings
Off-site prefabrication schedule Just-in-time delivery planning Craneage planning for heavy members Specialist erection team Storage planning on constrained site.
What would be required for erection?
Crane or telehandler
Temporary bracing Skilled carpentry team
Sequenced installation plan
Structural engineer sign-off.
How would erection been priced?
Pricing would include:
Material supply Fabrication costs
Specialist subcontractor labour
Crane hire
Transport
Temporary works
Preliminaries impact Risk allowances
I would also consider inflation risk if long lead items were involved.
If bearing capacity had been lower, how would that change your recommendation?
What was the allowable bearing pressure?
(Insert your real number if possible — e.g. 150–200 kN/m² typical for firm clay.)
* SI report confirmed allowable bearing capacity of approx. ___ kN/m²
* Engineer sized foundations accordingly
* I relied on structural design outputs to inform cost comparison
How did you ensure pad foundations were viable?
What risks did you highlight to the Client?
Did you consider differential settlement?
How did you quantify reinforcement?
What programme saving did pads provide?
How would you defend your comparison?