1. What was the weighting of the priority of Time vs cost and quality? – discussed with the Client
a. Time was the highest priority at 70%, cost was 20% and quality was 10%. The project had to be finished on time to allow the veterinary practice in, but also the project could not go over budget. This was discussed pre tender with the client
a. The client had the programme deadlines, an initial programme produced by the PM, then the contractor produced one which was vetted
b. Budget was based off cost plan previously.
a. These would be existing works that may not have been on the existing layouts, or works left in a particular state by the landlords enabling works which was not envisaged. For example, there was a historic drainage connection which required a survey to deduce whether the new connections can be tapped into this, or whether they would have to form a new one.
a. It was detailed out in the pricing schedule and clearly separated out.
a. The client wanted to retain control of the architectural design, but pass risk of MEP design onto contractor to complete design as it was not finalised. There was still possible amendments to the design that the client was aware of, to do with finishes to ensure it tied into the wider programme of works for continuity.
a. Yes as in the ICD the contractor is responsible for the design element of works, therefore any changes to that design that he makes, he bares the cost for.
a. Design documents relating to his designed portion, and O&M manuals
a. Section 2 of conditions, carrying out the works
a. Circa 40% / 230k
a. As design was at stage 4 for the architectural design, but the MEP design was not finalised and there were still unknowns, there was also no set standard for MEP design for the client, unlike the architectural works. The client wanted to retain control over the architectural works, as there were still some slight design alterations the client was aware of.
a. I originally advised the client that the project should be competitively tendered to at least 3 tenderers to ensure cost competition. b. Due to time constraints it was more beneficial to enter into negotiations with a single contractor and focus all time and energy to this, as well as getting them on board as early as possible to help advise on buildability of the scheme, rather than going through various analysis/reporting/approval processes which would be involved in a competitive tender.
a. Through prior experience working with the client where they proved themselves a trustworthy and successful contractor, as well as RLB endorsing this decision due to prior success on similar fast paced and risky schemes.
a. Consultant carried out the MEP design pre contract and acted as an advisory post contract to the client on a retained basis. The contractor completed the design.
a. For some of the works yes, but not for the rest of works. In this case it could be argued it was traditional procurement, as the design was completed prior to entering the contract, and the control remained with the client.
a. During construction I produced valuation assessments and drafted and issued the Payment Certificates in line with the contractual dates and procedures. I should have made this more clear in my documents.
a. The first interim valuation date (IVD) is 1 month after DoP. b. Due date is 7 days after this (QS has 7 days to agree with contractor). c. 5 days after due date CA must issue interim certificate. d. 14 days after due date is final date for payment
a. Option C as it is an existing building
You mentioned that the M&E was CDP, what does this mean, and how is it done?
This is a CDP analysis which was included in the contract docs. a separate section was detailed in the contract as the CDP portion, and separated in the CSA.
Do you require any documentation for CDP works?
Collateral warranties.
What are Collateral Warranties?
They provide a way to sue the subcontractor for damages in the default of the contractor, due to works that they designed and constructed.
How did you establish a procurement strategy for this project?
I discussed this with the client pre tender, advising to enter a competitive tender, but after consideration advising and choosing a negotiated tender purely due to timescales.
What was in the tender documents?
ER’s, CSA template, FoT, prelims, design info, PCI
How would tendering to other contractors increase cost certainty?
It would increase cost competition. Getting more favourable rates would also be beneficial for use on future potential change orders.
Were there any contract amendments?
The rectification period was extended to 12 months